Counties Impacted
Osage
Route Impacted
63
Work Type
Highway Realignment
Planning Phase

The current U.S. Route 63 corridor from south of U.S. Route 50 to the Maries River has a history of fatal and serious injury crashes. In the past 10 years, this corridor has seen 190 crashes that have resulted in seven fatalities, 12 serious injuries, and 80 minor injuries. To address the high rate of fatal and serious injury crashes, MoDOT is designing a new alignment for U.S. Route 63 while minimizing the impact on people, property, and the environment.

The existing U.S. Route 63 is primarily a two-lane roadway with 12-foot driving lanes and four-foot shoulders. The corridor studied is characterized by rolling hills with numerous sharp curves, driveways, and access points that contribute to uneven traffic flow, which increases the potential for high-crash rates. 

MoDOT is in the early stages of designing a new alignment for U.S. Route 63 along the preferred alternative corridor, as identified in the 2009 Environmental Impact Statement (EIS) and reaffirmed in the 2025 EIS re-evaluation. The proposed new road would be a four-lane divided highway connected to Westphalia via an interchange.

Image
Community members are a public meeting.

Public hearing

An open-house style public meeting will be held on Thursday, Aug. 21, 2025, at the Westphalia Knights of Columbus from 4:30 to 6 p.m. Members of the project team will be on hand to provide information, receive direct feedback, and answer questions from the community. There will be no formal presentation, so members of the public can come and go as they please. By participating and commenting, the public can help MoDOT determine what best serves the needs of the roughly 8,000 motorists who use the corridor on an average day while being responsible stewards of available funding.

PROJECT PROGRESS

Complete
Environmental Impact Statement

In 2006, U.S. Route 63 from U.S. Route 50 in Osage County to Rolla in Phelps County was ranked second out of 40 projects for future transportation needs by MoDOT and state planning partners. Subsequently, an Environmental Impact Statement (EIS) was conducted for this 47-mile section of U.S. Route 63. The EIS was completed in 2009 and identified the preferred alternative for improvements to this stretch of highway, divided into several regional sections.

The alternative corridors were evaluated based on public input, engineering, right-of-way requirements, environmental impacts, cultural resources, and construction costs. The EIS also considered leaving the existing corridor as is; however, that would not address the need to improve safety.

More information: https://www.modot.org/projects/us-route-63-environmental-impact-study-osage-maries-and-phelps-counties

milestone_icon
Complete
High Priority Unfunded Needs

As a result of collaborations with local planning partners, a new alignment for U.S. Route 63 from U.S. Route 50 to the Maries River (Section 1 of the EIS) was the first to move forward to a project due to its high rate of fatal and serious injury crashes.

This new alignment was included in Tier II of MoDOT’s High Priority Unfunded Needs in 2019, 2021, and 2022. As additional funding was made available for the 2023-2027 Statewide Transportation Improvement Program (STIP), this need moved forward as a construction project.

More about the High Priority Unfunded Need process is available at www.modot.org/unfundedneeds.

milestone_icon
Complete
EIS Re-evaluation

The original EIS for this section of U.S. Route 63 underwent a re-evaluation that was completed and approved by the Federal Highway Administration in June 2025. A National Environmental Policy Act re-evaluation was necessary because existing conditions, possible solutions, potential impacts, and related mitigation measures may have changed since the 2009 EIS.

Based on requests by local residents, MoDOT reconsidered one of the options not selected as the preferred alternative during the original study. The analysis concluded there were no notable differences, as the optional segment considered during the original EIS did not present a less impactful alternative. As a result, no changes were made to the preferred alternative.

More information: https://www.modot.org/projects/us-route-63-environmental-impact-study-osage-maries-and-phelps-counties

milestone_icon
In Progress
Planning, Design, and Right of Way Acquisition Phase

Based on the approved EIS, MoDOT is designing a new alignment for U.S. Route 63 in Osage County with the goal of improving safety while minimizing the impact on people, property, and the environment. These improvements will require right-of-way acquisition along with temporary and permanent easements. 

The estimated cost of engineering, right of way, and construction is $83.7 million, subject to change.

milestone_icon
In Progress
Public Input
Aug. 6 – Sept. 4, 2025

During the four-week comment period running Aug. 6 – Sept. 4, 2025, the community and interested parties will have multiple avenues to learn about, ask questions, and submit input regarding the proposed realignment. 

  1. In-person - An open-house-style public hearing will be held Thursday, Aug. 21, 2025, from 4:30 to 6 p.m. at the Westphalia Knights of Columbus located at 819 Highway 63 in Westphalia. The project team will be on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.
  2. Online - All meeting exhibits will be available on this website, and feedback may be submitted using the form below.
  3. By email – Send comments to CDCR@modot.mo.gov with the subject line: U.S. Route 63 realignment in Osage County.
  4. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by Sept. 4, 2025. Please reference: U.S. Route 63 realignment in Osage County.
milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is expected to be part of MoDOT's fall 2027 letting, when contractors submit competitive bids. If awarded by the Missouri Highways and Transportation Commission, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction could begin as early as fall 2027 and be completed in December 2029.

milestone_icon

FREQUENTLY ASKED QUESTIONS

What initiated this project?

In 2006, MoDOT and state planning partners presented 40 projects to address future transportation needs and ranked U.S. Route 63 from U.S. Route 50 in Osage County to Rolla in Phelps County as the second-highest need. Subsequently, an Environmental Impact Statement (EIS) was completed in 2009. 

Local planning partners reaffirmed the U.S. Route 63 from U.S. Route 50 to the Maries River segment (Section 1 of the EIS) as a high priority for the region. As a result, it was included in Tier II of MoDOT’s High Priority Unfunded Needs in 2019, 2021, and 2022.

As additional funding was made available for the 2023-2027 Statewide Transportation Improvement Program (STIP), this need moved forward as a construction project. This initiated a re-evaluation of the 2009 EIS, which was completed and approved by the Federal Highway Administration in June 2025.

This project will realign U.S. Route 63 from south of U.S. Route 50 to the Maries River, expanding the current two-lane highway to a four-lane divided highway, in order to address safety concerns. In the past 10 years, this corridor has seen 190 crashes that have resulted in seven fatalities, 12 serious injuries, and 80 minor injuries. 

Yes. The existing two-lane roadway with 12-foot driving lanes would be upgraded to a four-lane divided highway connected to Westphalia via an interchange.

With more than 8,000 average daily travelers, the existing U.S. Route 63 has more traffic than is ideal for a two-lane highway. Adding a center turn lane would not help with the number of vehicles on the road. Nor would it reduce the conflict points created by left-turning movements.

Direct access from the proposed U.S. Route 63 and the existing Route 133 was considered. Though multiple options for direct access were looked at, none moved forward due to safety considerations and increased right-of-way impact.
Building an interchange at Route 133 would involve changing the alignment of Route 133, building excessively long ramps, and disrupting more right of way than the current proposal.

The proposed new alignment of U.S. Route 63 will improve safety by adding additional lanes and increasing roadway capacity for the more than 8,000 travelers who use the road each day, reducing the number of sharp curves, and minimizing the number of conflict points.

Traffic impacts will not be determined until the new alignment is further along in the design process. 

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference U.S. Route 63 realignment in Osage County on your inquiries. 

Sign up for project-specific updates using the form below.

Project News

  • Input sought on realigning U.S. Route 63 in Osage County

    07/30/2025

     

    JEFFERSON CITY, Mo The current U.S. Route 63 corridor from south of U.S. Route 50 to the Maries River has a history of fatal and serious injury crashes. The Missouri Department of Transportation (MoDOT) is exploring a new realignment for U.S...

Webform
Have Project Questions or Feedback? Use the form below to share your questions, thoughts and comments.
*
*
*

Your email address shared here will not be used for any purpose other than communicating about this project.