Deer Creek Bridge Redeck on Route 100 in Osage County

Below are details, resources and news about the deck replacement on the Route 100 bridge over Deer Creek, located west of Chamois.

This bridge was included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. Check out the Focus on Bridges page for more information about the program. 

Project Details

When: 

The project took place in 2022.

Cost: 

The project cost is $1,408,489. It is part of a project that will also replace the Cedar Creek Bridge on Route 100. 

Work Taking Place

The project consisted of replacing the bridge deck.

Project Milestones

Complete
Public Comment Period
June 11 - 25, 2021
milestone_icon
Complete
Bid Awarded
February 2, 2022

The Missouri Highways and Transportation Commission awarded the contract for this project to E & C Bridge, LLC., which submitted the low bid of $1,408,489 (project awarded in combination with the Cedar Creek bridge replacement project on Route 100 in Osage County). 

milestone_icon
Complete
Construction of New Bridge Deck
May-July, 2022

Work was completed on July 11, 2022. Occasional lane closures are possible until July 22, for seeding operations.

milestone_icon

Project News & Updates

  • Deer Creek Bridge Improvement Project Begins Monday

    05/24/2022

    OSAGE COUNTY Weather permitting, contractors working for the Missouri Department of Transportation (MoDOT) will begin the process of replacing the deck of the Route 100 bridge over Deer Creek, west of Chamois, beginning Monday, May 23.