Counties Impacted
Callaway
Route Impacted
54
OO
Work Type
Roundabout Construction
Completed

Below are details, resources and news about the improvements to the Route OO and U.S. Route 54 Ramp intersections in Callaway County.

Project Details (updated Dec 21, 2023)

When:

The Notice to Proceed date is May 9, 2023, with a contract completion date of Nov. 1, 2023.




Cost: 

A $1,124,421.80 contract was awarded to Sam Gaines Construction, Inc.




Work Taking Place

The project consists of building a roundabout at the intersection of the eastbound U.S. Route 54 exit and entrance ramps with Route OO and intersection improvements at the westbound Route 54 exit and entrance ramps. The proposed intersection layout will improve traffic flow and safety at the ramp intersections.




Traffic Impact: 

The eastbound U.S. Route 54 ramp intersection at Route OO will be closed for approximately one month to construct the roundabout.  Traffic will be detoured to other state routes in the area.  During construction at the westbound U.S. Route 54 ramp intersection, work will be done under traffic control.

Project Milestones

Complete
Public Feedback Period
November 7-30, 2022
milestone_icon
Complete
Public Meeting
Thursday, December 1, 2022

Meeting held at the Holts Summit Municipal Building. 

milestone_icon
Complete
Contract Award
April 5, 2023

The $1,124,421.80 contract was awarded to Sam Gaines Construction, Inc. during the April 2023 meeting of the Missouri Highways and Transportation Commission (MHTC). 

milestone_icon
Complete
Work Begins

The contractor plans to begin work May 22, 2023, with all work scheduled to be completed on or before July 16, 2023. The schedule is subject to change.

The work on the east side of the interchange required the complete closure of Route OO (Simon Boulevard) over U.S. Route 54 and the on/off ramps for northbound U.S. Route 54. The closure began Tuesday, May 30, and Route OO and the ramps reopened on Thursday, June 29.

milestone_icon
Complete
Project Completion

All road closures are expected to be complete and reopened to the public on or before June 30. The contractor's current plan is to have all work completed on or before July 16. This date is subject to change.

milestone_icon

Project News and Updates

  • Road to close Tuesday in Holts Summit

    05/25/2023

    JEFFERSON CITY, Mo. – An intersection improvement project already underway will close parts of the U.S. Route 54 and Route OO interchange in Holts Summit next week. Contractors from Sam Gaines Construction, Inc., working with the Missouri Department...