Counties Impacted
Webster
Project Status
Planning Phase
Route Impacted
U.S. Route 60
Route A
Route Z

Project Timeline

April 26, 2022
Public meeting
4:30-6 p.m. at Diggins Baptist Church
3700 Normandy Road, Seymour, MO 65746
Spring 2024
Project awarded to construction contractor
Fall 2024
Construction begins
2026
Project complete

Project highlights:

  • New interchange at U.S. Route 60 and Webster County Route A
  • Build bridge over Route 60 and BNSF Railroad
  • Connect Route NN to new Route A interchange
  • Roundabout at new Route NN/Route A intersection
  • Construct south Outer Road between Route Z in Fordland and Route A in Diggins along the south side of BNSF Railroad
  • Preliminary layout for new interchange at Route Z and new north Outer Road in Fordland
  • Remove 9 railroad crossings: Route NN, Greenbriar Drive,  Honor Camp Lane, Tandy Road, Hummingbird Lane, Bluebird Lane, 3 additional private drives
  • Remove 9 Route 60 highway intersections/private access: Routes A, NN, and O and Bluebird Ln, Hummingbird Ln (south side), Honor Camp Ln (south side), Greenbriar Dr, and 2 private accesses
  • Estimated project cost of Route A interchange and new Outer Road: $25.5 million
  • Estimated project cost of Route Z interchange: $20.7 million (currently unfunded)
  • Preliminary layout alternatives for a new Outer Road in Diggins along the south side of BNSF Railroad (currently unfunded)
  • Preliminary layout alternatives for a new Outer Road in Diggins along the north side of U.S. Route 60 (currently unfunded)

Traffic Impacts:

  • Lane closures on US 60 at times
  • Narrowed lanes at times
  • During higher traffic volume, drivers can expect occasional delays
  • Crews and equipment close to traffic
  • Temporary partial driveway and access disruptions
Webform

PROJECT UPDATES