Districts Impacted
Counties Impacted
Webster
Project Status
Planning Phase
Route Impacted
U.S. Route 60
Route A
Route Z
Project Timeline
April 26, 2022
Public meeting
4:30-6 p.m. at Diggins Baptist Church
3700 Normandy Road, Seymour, MO 65746
4:30-6 p.m. at Diggins Baptist Church
3700 Normandy Road, Seymour, MO 65746
Spring 2024
Project awarded to construction contractor
Fall 2024
Construction begins
2026
Project complete
Project Displays/Maps
- Pathways of Progress: A Property Owners Guide on Land Acquisition for Transportation Improvements
- US 60 Webster Co Rt A Diggins Fact Sheet
- Route NN Connection Options
- Box School Loop South Outer Road Options
- Route A in Diggins Option 1
- Route A in Diggins Option 2
- Route A in Diggins Option 3
- Route A in Diggins Option 4
- Route A in Diggins Option 5
- Route Z in Fordland Option 1
- Route Z in Fordland Option 2
- Route Z in Fordland Option 3
- Route Z in Fordland Option 4
- Route O in Diggins Connection Option 1
- Route O in Diggins Connection Option 2
- Route O in Diggins Connection Option 3
- South Outer Road Options
Project highlights:
- New interchange at U.S. Route 60 and Webster County Route A
- Build bridge over Route 60 and BNSF Railroad
- Connect Route NN to new Route A interchange
- Roundabout at new Route NN/Route A intersection
- Construct south Outer Road between Route Z in Fordland and Route A in Diggins along the south side of BNSF Railroad
- Preliminary layout for new interchange at Route Z and new north Outer Road in Fordland
- Remove 9 railroad crossings: Route NN, Greenbriar Drive, Honor Camp Lane, Tandy Road, Hummingbird Lane, Bluebird Lane, 3 additional private drives
- Remove 9 Route 60 highway intersections/private access: Routes A, NN, and O and Bluebird Ln, Hummingbird Ln (south side), Honor Camp Ln (south side), Greenbriar Dr, and 2 private accesses
- Estimated project cost of Route A interchange and new Outer Road: $25.5 million
- Estimated project cost of Route Z interchange: $20.7 million (currently unfunded)
- Preliminary layout alternatives for a new Outer Road in Diggins along the south side of BNSF Railroad (currently unfunded)
- Preliminary layout alternatives for a new Outer Road in Diggins along the north side of U.S. Route 60 (currently unfunded)
Traffic Impacts:
- Lane closures on US 60 at times
- Narrowed lanes at times
- During higher traffic volume, drivers can expect occasional delays
- Crews and equipment close to traffic
- Temporary partial driveway and access disruptions
Webform
PROJECT UPDATES
-
MoDOT: U.S. Route 60 and Webster County Routes A and Z Interchanges Project in Diggins and Fordland
Diggins & Fordland, Webster County – Area residents are invited to a public meeting to discuss three proposed projects to reduce traffic delays and increase safety at U.S. Route 60 and the intersections of Webster County Route A in Diggins and Route...