Where: Webster County Route A CLOSED just North of Normandy Road in Diggins
When: Monday, November 10, until Thursday, November 20
What: Contractor crews will connect Route A to the new North Outer Road as part of the U.S. Route 60 and Webster County Route A Interchange improvements project between Diggins and Fordland. When the work on Route A is complete and the route is reopened, traffic will be detoured to Route O using the new North Outer Road to connect with U.S. Route 60.
Traffic Impacts:
- Webster County Route A CLOSED just North of Normandy Road in Diggins
- U.S. Route 60 lane Closures between Webster County Route A and Route O in Diggins
- Eastbound Route 60 passing lane Closed
- Westbound Route 60 driving lane Closed
- U.S. Route 60 Open
- Drivers urged to find alternate routes
- No signed detours planned
- Signs and message boards will alert drivers approaching the work zone
- Check MoDOT’s Traveler Information Map for road closures/traffic impacts
Weather and/or construction delays could alter the work schedule.
To get project updates or sign up for project emails, visit: https://www.modot.org/projects/us-route-60-route-and-route-z-interchange-improvements-webster.
Project Summary:
- Build interchange at U.S. Route 60 and Webster County Route A
- Build bridge over Route 60 and BNSF Railroad
- Connect Route NN to new Route A interchange with north Outer Road
- Roundabout at new Route NN/Route A intersection south of Route 60
- Construct south Outer Road between Route Z in Fordland and Route A in Diggins along the south side of BNSF Railroad
- Remove nine railroad crossings: Route NN, Greenbriar Drive, Honor Camp Lane, Tandy Road, Hummingbird Lane, Bluebird Lane, three additional private drives
- Remove nine Route 60 highway intersections/private access: A, NN, Route O (right-in, right-out only), as well as Bluebird Lane, Hummingbird Lane (south side), Honor Camp Lane (south side), Greenbriar Drive, and two private accesses
Contractor: Capital Paving & Construction LLC, Jefferson City
The awarded construction cost is $39.8 million.
The project is scheduled for completion in December 2027.
END 
 
 For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
 