Counties Impacted
Webster
Route Impacted
60
C
K
Work Type
Intersection Improvements
Planning Phase

PROJECT TIMELINE

March 7, 2023
Public meeting held at Seymour High School to gather feedback on U.S. Route 60 Intersection Improvements Project concepts
milestone_icon
May 13, 2024 from 4:30-6 p.m.
Public meeting held Seymour Middle School Cafeteria, 501 E Clinton Ave, Seymour
to show plans for the U.S. Route 60 Intersection Improvements Project
milestone_icon
2025
Begin securing land for project
milestone_icon
Summer 2026
Final Project Design
milestone_icon

Project highlights:

  • New interchange at U.S. Route 60 and Webster County Route C/K to improve safety and traffic flow
  • Realign Route K to new interchange and connect local Garfield Street to new interchange
  • Construct Outer Roads for improved connectivity north of Route 60, from Enterprise Drive to Skyline Road
  • U.S. Route 60 Intersection Improvements at Clinton Avenue
  • Remove 2 signalized intersections and crossovers: Route C/K and Clinton Avenue
  • Remove 2 unsignalized intersections and crossovers: Skyline Drive and Lynch Drive
  • Estimated project cost: $30.7 million

 Traffic Impacts:

  • Lane closures on Route 60 at times
  • Narrowed lanes at times
  • During higher traffic volume, drivers can expect occasional delays
  • Crews and equipment close to traffic
  • Temporary partial driveway and access disruptions

Join us at the Public Meeting on Monday, May 13, from 4:30 p.m. - 6 p.m. at Seymour Middle School, 501 E Clinton Ave, Seymour.

If you are unable to attend, beginning Monday, May 13 through Monday, May 27, you can leave your comments and questions on the form that will be available below.

Webform