Counties Impacted
St. Francois
Iron
Route Impacted
221
Work Type
Curve Improvements
Planning Phase

Project Timeline

Clearing Work
Jan. 2024

Clearing work is being completed in preparation for this project. There will be minimal impacts to traffic. Flaggers may be necessary at times as equipment is unloaded.  

milestone_icon
Tentative Letting
May 2024
milestone_icon
Construction Begins
As early as Summer 2024 (tentative)
milestone_icon

Project Details

The project consists of an asphalt overlay from Farmington, Missouri to Pilot Knob, Missouri with a 4200’ section of new roadway being built near Henson Road at Doe Run, Missouri. The new section of roadway will replace five existing curves with two more gradual curves and provide less steep vertical grades.

For More Information

Contact Photo
Benji Philpot
Benji Philpot
Title
District Construction & Materials Engineer
Department
Southeast District
Contact Info

(573) 472-5371