Counties Impacted
Franklin
St. Louis
Route Impacted
T
Work Type
Pavement Resurfacing

What is the current situation?

The Missouri Department of Transportation will work on pavement resurfacing, pavement repair, slide repairs, sign replacement and upgrading guardrail from Route 100 in Franklin County on the west to Route 100 in St. Louis County on the east.  There will also be bridge deck sealing over Labadie Creek. 

Project Milestones

Not Started
Project Award Date

May 2025 

milestone_icon
Not Started
Notice to Proceed

June 2025 

The Notice to Proceed indicates the contract may begin work on a project per the terms of the contract. It establishes a clear start date and specify milestones and timelines within the project. 

milestone_icon
Not Started
Construction Complete

Late Fall 2026 

milestone_icon

Will there be any right of way acquisitions? 

MoDOT will need to purchase permanent easements for construction. A right of way representative will be contacting affected property owners.

What is the length of the project? 

This project is approximately 14 miles long. 

How much will the project cost? 

The cost of construction is estimated at $5.5 million. 

Project Contacts

Shirley Norris
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info

Office: (314)-453-5032

Cell: (314)-565-5648

E-mail: Shirley.Norris@modot.mo.gov