Counties Impacted
Franklin
Project Status
Planning Phase

Project Milestones

In Progress
Project design
In Progress
Acquiring needed right of way
Not Started
Contract awarded

April 2019.  Date is subject to change.

Not Started
Construction begins

June 2019.  This date is subject to change.

Route Impacted

The Missouri Department of Transportation is working on plans to upgrade the sidewalks to current Americans with Disabilities Act (ADA) standards and resurface a section of Route 47 in Washington, Missouri.

These improvements along Route 47 stretch from Third Street to Norwood Trailer Court.  MoDOT will need to acquire right of way for this project and will need to make adjustments to existing utilities. 

Maps, plans and other detailed information are available for the public to see and copy at the office of the St. Louis District Engineer of the Missouri Department of Transportation, 1590 Woodlake Drive, Chesterfield, Missouri 63017-5712.

To give impacted property owners a chance to see some material without traveling to Chesterfield, the following information about the project is presented:

Project Contacts

Contact Photo
Thumbnail
Judy Wagner
Title
Area Engineer, Franklin and Jefferson Counties
Contact Info

Office: (314) 453-5021
E-mail: judy.wagner@modot.mo.gov