Districts Impacted
PROJECT DETAILS
MoDOT will be making safety improvements along U.S. 24 just east of east of Wilson Ave. to just west of Sterling Ave. Improvements include a 5-lane typical section with curb and gutter, enclosed drainage storm sewers, raised concrete islands, traffic signal improvements, and signing and pavement marking improvements. A 10-foot multi-use path is also proposed along the south side of the roadway with a 5-foot sidewalk along the north side of the roadway.
The main goal of this project is to improve safety and mobility along the U.S. 24 Highway just east of Wilson Ave. to just west of Sterling Ave. After reviewing the types and locations of crashes within the corridor, it was determined that the best way to address the concerns and improve safety is to modify the roadway to a 5-lane section with a two-way left turn lane. In addition, there are intersections that will be improved with upgrading or replacing traffic signals. In order to improve bicycle and pedestrian safety, this project will include additional crossings at traffic signals, a new shared use path, and new sidewalks and existing sidewalk upgrades. Drainage will be improved through the corridor. Access to businesses along the corridor will also be improved.
This is the third and final phase of the project. Phases 1 and 2 were let in combination in May 2023. Construction is scheduled to begin in the summer of 2023 and the project is scheduled to be completed in the summer of 2026.
TRAFFIC IMPACTS AND COSTS
Lane closures on U.S. 24 and some side street closures will occur during construction. Local businesses may see impacts to their access during construction.
This project is funded through a partnership between the City of Independence and MoDOT and is currently estimated at $5 million.
This is the third and final phase of the project.
Online Comment Period Information
MoDOT will host an online comment period for the third and final phase of the project. The comment period will be open from 4 p.m. Tuesday, July 25 until 4 p.m. on Tuesday, Aug. 8. If you need more information, please refer to the contact information and comment form available below.

Project Plans & Timeline
- Project Plans
- Timeline
-
This is the third and final phase of the project. Phases 1 and 2 were let in combination in May 2023. Construction is scheduled to begin in the summer of 2025 and the project is scheduled to be completed in the summer of 2026.
-
Please note preliminary plans are subject to change.
-

Need More Information?
We're here to help. If you need additional information, you may contact MoDOT Kansas City Area Engineer Jill Bruss or Project Manager Chris West.
- Jill Bruss, MoDOT Area Engineer
- Email: jill.bruss@modot.mo.gov
- Christopher West, Project Manager
- MoDOT Customer Service Line: 1-888-275-6636

Share Your Comments!
Online Comment Information
MoDOT accepted comments on Phase 3 of this project (U.S. 24 just east of east of Wilson Ave. to just west of Sterling Ave.) from 4 p.m. on Tuesday, July 25 until 4 p.m. on Tuesday, Aug. 8. The comment form is now closed. If you need more information, please refer to the contact information above to request more information.
NEWS RELEASES
-
REVISED: Permit requires closure of Blue Pkwy between NE Joel Ave. and Milton Thompson Ave., ongoing-July 15
JACKSON COUNTY – Permit work will require the closure of Blue Parkway between NE Joel Ave. and Milton Thompson Rd., ongoing -July 15 (approximately) (revised from March 26 -June 15). This closure is for the construction of a roundabout east of NE...
-
CLOSURES scheduled for repaving work on SB I-35 in downtown Kansas City, June 20-23
JACKSON COUNTY – Crews will perform repaving work requiring the following closures on SB I-35 from the interchange of I-35 and I-670 and ending at the ramps to I-70, Broadway Blvd., and SB U.S. 169, June 20-23.
The following CLOSURES will be in place...
-
CLOSURE scheduled for MO 150 at I-49 for maintenance operations, 6 a.m.-6 p.m., Sunday, June 22
JACKSON COUNTY – Crews will close WB/EB MO 150 between W. Frontage Rd and White Ave. under I-49 for maintenance operations including lighting, signing, signals, striping, and bridge repairs at the intersection.
The following will be closed from 6 a...
-
REVISED: Lane closures scheduled for repaving work on NB/SB I-35, evening/overnight, June 23 -July 26
JACKSON COUNTY – Crews will perform repaving work requiring double lane closures and ramp closures on NB/SB I-35 from the state line (Cambridge Cir.) to the I-670 interchange, evening and overnight, 7 p.m. until 6:30 a.m., June 23 – July 26...
-
Lane closures scheduled for pavement repair on EB I-70 at Blue Ridge Cutoff, June 19-20
JACKSON COUNTY – Crews will complete pavement repair work requiring a double lane closure on EB I-70 at Blue Ridge Cutoff, evening and overnight, beginning at 7 p.m. on June 19 until 6 a.m. on June 20.
Motorists are reminded to slow down and pay...