Districts Impacted
PROJECT DETAILS
MoDOT will be making safety improvements along U.S. 24 just east of east of Wilson Ave. to just west of Sterling Ave. Improvements include a 5-lane typical section with curb and gutter, enclosed drainage storm sewers, raised concrete islands, traffic signal improvements, and signing and pavement marking improvements. A 10-foot multi-use path is also proposed along the south side of the roadway with a 5-foot sidewalk along the north side of the roadway.
The main goal of this project is to improve safety and mobility along the U.S. 24 Highway just east of Wilson Ave. to just west of Sterling Ave. After reviewing the types and locations of crashes within the corridor, it was determined that the best way to address the concerns and improve safety is to modify the roadway to a 5-lane section with a two-way left turn lane. In addition, there are intersections that will be improved with upgrading or replacing traffic signals. In order to improve bicycle and pedestrian safety, this project will include additional crossings at traffic signals, a new shared use path, and new sidewalks and existing sidewalk upgrades. Drainage will be improved through the corridor. Access to businesses along the corridor will also be improved.
This is the third and final phase of the project. Phases 1 and 2 were let in combination in May 2023. Construction is scheduled to begin in the summer of 2023 and the project is scheduled to be completed in the summer of 2026.
TRAFFIC IMPACTS AND COSTS
Lane closures on U.S. 24 and some side street closures will occur during construction. Local businesses may see impacts to their access during construction.
This project is funded through a partnership between the City of Independence and MoDOT and is currently estimated at $5 million.
This is the third and final phase of the project.
Online Comment Period Information
MoDOT will host an online comment period for the third and final phase of the project. The comment period will be open from 4 p.m. Tuesday, July 25 until 4 p.m. on Tuesday, Aug. 8. If you need more information, please refer to the contact information and comment form available below.

Project Plans & Timeline
- Project Plans
- Timeline
-
This is the third and final phase of the project. Phases 1 and 2 were let in combination in May 2023. Construction is scheduled to begin in the summer of 2025 and the project is scheduled to be completed in the summer of 2026.
-
Please note preliminary plans are subject to change.
-

Need More Information?
We're here to help. If you need additional information, you may contact MoDOT Kansas City Area Engineer Jill Bruss or Project Manager Chris West.
- Jill Bruss, MoDOT Area Engineer
- Email: jill.bruss@modot.mo.gov
- Christopher West, Project Manager
- MoDOT Customer Service Line: 1-888-275-6636

Share Your Comments!
Online Comment Information
MoDOT accepted comments on Phase 3 of this project (U.S. 24 just east of east of Wilson Ave. to just west of Sterling Ave.) from 4 p.m. on Tuesday, July 25 until 4 p.m. on Tuesday, Aug. 8. The comment form is now closed. If you need more information, please refer to the contact information above to request more information.
NEWS RELEASES
-
Lane closures scheduled for EB/WB I-470 from Hillcrest Rd. to Raytown Rd., June 2-16
JACKSON COUNTY – Crews will replace the barrier wall requiring the closure of the inside lane on EB/WB I-470 from Hickman Mills Dr. to Raytown Road, beginning at 6 a.m. on Monday, June 2 through Monday, June 16 (approximately).
This work is part of...
-
REMINDER: Closures scheduled for WB I-670 in downtown Kansas City, May 30-June 2, June 6-9
JACKSON COUNTY – Crews will perform repaving work requiring the following closures on WB I-670 from Troost Ave. to near 18th St. in Kansas, May 30-June 2 and June 6-9.
7 p.m. on Friday, May 30 until 6 a.m. on Monday, June 2 (approximately) and 7 p.m...
-
Kansas City area maintenance work for May 27-30
LEE’S SUMMIT, MO – The Missouri Department of Transportation will be performing maintenance work throughout the Kansas City region from May 27-30. No maintenance work is scheduled for the Memorial Day holiday on May 26. All work is weather permitting...
-
Mural installation completed on the new Buck O'Neil Bridge
Kansas City, MO - The Missouri Department of Transportation (MoDOT), Buck O’Neil Bridge Project Team, Massman Clarkson Joint Venture in partnership with Art in the Loop Foundation (AILF), and artist Phil “Sike Style” Shafer announce the completion of...
-
Lane closure scheduled for KC Scout camera installation on SB U.S. 71, May 28-29
JACKSON COUNTY – Crews will close one lane on SB U.S. 71 between 18th St. and 22nd St., from 9 a.m. until 3 p.m. on Wednesday, May 28 and Thursday, May 29.
Motorists are advised to plan ahead and be vigilant of work in the area. All work is weather...