Districts Impacted
PROJECT DETAILS
MoDOT will be making safety improvements along U.S. 24 just east of east of Wilson Ave. to just west of Sterling Ave. Improvements include a 5-lane typical section with curb and gutter, enclosed drainage storm sewers, raised concrete islands, traffic signal improvements, and signing and pavement marking improvements. A 10-foot multi-use path is also proposed along the south side of the roadway with a 5-foot sidewalk along the north side of the roadway.
The main goal of this project is to improve safety and mobility along the U.S. 24 Highway just east of Wilson Ave. to just west of Sterling Ave. After reviewing the types and locations of crashes within the corridor, it was determined that the best way to address the concerns and improve safety is to modify the roadway to a 5-lane section with a two-way left turn lane. In addition, there are intersections that will be improved with upgrading or replacing traffic signals. In order to improve bicycle and pedestrian safety, this project will include additional crossings at traffic signals, a new shared use path, and new sidewalks and existing sidewalk upgrades. Drainage will be improved through the corridor. Access to businesses along the corridor will also be improved.
This is the third and final phase of the project. Construction will begin in late Fall 2025 and will be completed by late Fall/early Winter of 2026.
Phases 1 and 2 were let in combination in May 2023 and will be completed and construction is in progress and will be completed in spring/summer of 2026.
TRAFFIC IMPACTS AND COSTS
Lane closures on U.S. 24 and some side street closures will occur during construction. Local businesses may see impacts to their access during construction.
This project is funded through a partnership between the City of Independence and MoDOT and is currently estimated at $5 million.
This is the third and final phase of the project.
Online Comment Period Information
MoDOT hosted an online comment period for the third and final phase of the project. The comment period will be open from 4 p.m. Tuesday, July 25, 2025 until 4 p.m. on Tuesday, Aug. 8, 2025. If you need more information, please refer to the contact information and comment form available below.

Project Plans & Timeline
- Project Plans
- Timeline
-
This is the third and final phase of the project. Phases 1 and 2 were let in combination in May 2023. Construction began in 2025 and the project is scheduled to be completed in the summer of 2026.
-
Please note preliminary plans are subject to change.
-

Need More Information?
We're here to help. If you need additional information, you may contact MoDOT Kansas City Area Engineer Jill Bruss or Project Manager Chris West.
- Jill Bruss, MoDOT Area Engineer
- Email: jill.bruss@modot.mo.gov
- Christopher West, Project Manager
- MoDOT Customer Service Line: 1-888-275-6636

Share Your Comments!
Online Comment Information
MoDOT accepted comments on Phase 3 of this project (U.S. 24 just east of east of Wilson Ave. to just west of Sterling Ave.) from 4 p.m. on Tuesday, July 25 until 4 p.m. on Tuesday, Aug. 8. The comment form is now closed. If you need more information, please refer to the contact information above to request more information.
NEWS RELEASES
-
CLOSURE scheduled for repaving on WB I-470 from Raytown Rd. to Hickman Mills Drive, July 25-28
JACKSON COUNTY – Crews will CLOSE WB I-470 from Raytown Rd. to Hickman Mills Drive from 8 p.m. on Friday, July 25 until 6 a.m. on Monday, July 28.
The following will be CLOSED from 8 p.m. on Friday, July 25 until 6 a.m. on Monday, July 28:
- Westb...
-
Improve I-70 KC: Lane/ramp closures on I-70 near 23rd St. for girder installation, July 18-20
JACKSON COUNTY – Crews will be conducting lane and ramp closures on Interstate 70 near 23rd St. from Fri., July 18 at approximately 6:30 a.m., until Sun., July 20 at approximately 6 a.m., for girder installation at the 23rd St. bridge over I-70.
Fri...
-
EXTENDED Daily lane closures scheduled for MO-7 in Pleasant Hill, NOW-Nov. 1
CASS COUNTY – Crews will make daily lane closures on MO-7 at various locations between 163rd Street and Richland Parkway in Pleasant Hill, Monday-Saturday, 6 a.m. – 6 p.m., NOW-Nov. 1 (extended from July 18). This work is for ADA sidewalk...
-
REMINDER: Online comment period regarding the U.S. 71 bridges over Bannister Rd., ONGOING-July 24
REMINDER: JACKSON COUNTY – The Missouri Department of Transportation (MoDOT) is hosting an online comment period regarding the replacement of the U.S. 71 bridges over Bannister Rd. (MO Route W). This online comment period opened at 5 p.m. on July 10...
-
Overnight lane closures on I-435 between US-24 and the MO River for resurfacing, July 14-Aug. 31
JACKSON COUNTY – Crews will be performing various overnight lane closures on northbound and southbound Interstate 435 between U.S. Highway 24 and the Missouri River for resurfacing operations. Work is scheduled to take place from Mon., July 14 until...