Districts Impacted
PROJECT TIMELINE
Ash Grove High School Library, 100 N Maple Ln, Ash Grove
This is a come-and-go style meeting with no formal presentation. If you cannot attend, please review the project information and complete the comment form below by March 16.
Project Information
- Replace the Greene County Route F bridge over Sac River between County Route 114 and County Route 116 south of Ash Grove
- New bridge will be 10 feet wider and 9 feet longer than the current bridge
Traffic Impacts
- Route F over Sac River will be Closed to traffic for up to 4 months
- Signed Detour: Route T and Route 266
Bridge Facts
- Built in 1936
- Old bridge is 22 feet wide, 335 feet long
- Carries 874 vehicles a day
- Current bridge is in need of frequent maintenance
Estimated Total Project Cost: $4.1 million
This project is being let with the U.S. Route 160 Culvert Replacement Project in Ash Grove found here.
Project Updates
-
MoDOT: U.S. Route 160 Culvert Replacement in Ash Grove & Greene County Route F Bridge Replacement
Ash Grove, Greene County – Those interested in the U.S. Route 160 Culvert Replacement Project in Ash Grove & Greene County Route F Bridge Replacement Project south of Ash Grove are invited to a public meeting to discuss proposed improvements and...
Frequently Asked Questions:
Will there be a signed detour?
Yes, a signed detour for the Route F bridge closure includes Route T and Route 266.
How long will the Route F bridge be closed?
The Greene County Route F Bridge over Sac River will be closed for up to 4 months.
Will I be able to access my property on Route F?
Drivers will have access to driveways and entrances on either end of the work zone, but will not be able to travel through the work zone.
Will MoDOT need to acquire additional right-of-way for these projects?
Yes. Additional right-of-way will be needed to construct the project. The new construction will require the acquisition of right-of-way and temporary easements from property owners. Please review the exhibits for additional information. A Right of Way representative will be contacting affected landowners to begin the acquisition process. For more information on the acquisition process, please see the Pathways of Progress display above.
The last day to leave comments on this project is March 16.
Project Contacts
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info
Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Ozarks Transportation Organization: Greene & Christian Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Bud Sherman
Title
Transportation Project Manager
Department
Design
Contact Info
Email: Bud.Sherman@modot.mo.gov
For the most efficient response, please contact Bud via email.
Phone: (417) 895-7690
Email: Bud.Sherman@modot.mo.gov
For the most efficient response, please contact Bud via email.
Phone: (417) 895-7690