Counties Impacted
Montgomery
Route Impacted
E
Y
Work Type
Bridge Replacement
Highway Feature
Interstate 70
Planning Phase

Project Summary

The Missouri Department of Transportation (MoDOT), working with its consultant Jacobs Engineering Group, is preparing for a bridge replacement and interchange improvement project at Routes E/Y, over Interstate 70 in Jonesburg in Montgomery County. 

The purpose of the project is to replace the existing aging bridge structure in the current location with a wider bridge, allowing for the addition of shoulders. 

This project will require periodic closures and lane reductions on various sections of the interchange, including I-70, Routes E/Y, and interchange ramps, to facilitate construction work. As necessary, traffic will be diverted around closures utilizing signed detour routes.

Improvements at this location include:

  • Replacing the Routes E/Y bridge in the existing location
  • A new 44’ wide bridge consisting of 12’ driving lanes and 10’ shoulders
  • Interchange improvements to accommodate the proposed I-70 template with the addition of a third lane, and improved bridge clearance and span lengths

** This project is scheduled to be start after the completion of the Bridge Replacement and Interchange Improvements Project on Routes A/B, over Interstate 70 near Pendleton in Warren County.

Project Milestones

Public Meeting

February 3, 2025

milestone_icon
Letting

February 2025

milestone_icon
Under Contract

Spring 2025

Contractor: TBD
Contract Amt: TBD

milestone_icon
Not Started
Under Construction

2026

milestone_icon
Project Completion

Fall 2026

milestone_icon
Image
Public engagement

Project Information and Public Engagement


Public Meeting
February 3, 2025 | 5 - 7 p.m.
Location: Commons Area – Warrenton High School, 803 Pinckney Street, Warrenton, MO 63383

For more accessibility assistance, please contact us at improvei70east@modot.mo.gov

Sign up for E-update and text alerts.

News Releases

Project Map

Embed
Bridge Replacement Project on Routes E/Y, over Interstate 70 in Jonesburg in Montgomery County
Is Responsive
Embed Code

Project Contacts

Contact Photo
Kim Trainor portrait
Kim Trainor, P.E.
Title
Improve I-70: East Project Team Director
Department
Central Office
Contact Photo
Jeff Neimeyer Portrait
Jeff Niemeyer
Title
Area Engineer
Department
Northeast District
Contact Info

Email: jeffrey.niemeyer@modot.mo.gov 

Phone: (573) 808-3562

 

Frequently Asked Questions

How much does the project cost?  

Approximately $4 million.

What are the anticipated impacts?  

Various traffic impacts will be in place as the project progresses. Customers can anticipate temporary traffic impacts throughout the project due to periodic closures and lane reductions on various sections of the interchange and surrounding routes to facilitate construction work. As necessary, traffic will be diverted around the closed areas utilizing signed detour routes.  MoDOT will make every reasonable effort to reduce delays due to construction. More information regarding traffic impacts will be shared through news releases and social media for each stage of construction as details become available.

How will construction affect local businesses?

MoDOT is committed to ensuring that businesses and patrons near the project limits maintain access throughout the duration of the project.

How can I stay updated about the project? 

Stay updated on news about roadwork in your area by signing up for emails at eUpdates at MoDOT.org

Who can I contact if I have further questions? 

Questions about the project may be directed to Kimberly Trainor, MoDOT's project manager overseeing the project at kimberly.trainor@modot.mo.gov or Jeff Niemeyer, Area Engineer, at jeffrey.niemeyer@modot.mo.gov