This project will make improvements to the existing pedestrian facilities and sidewalks along 2.5 miles of Route D (Page Ave.) between Oak Ave. (just east of US-67) and Innerbelt Business Center Dr. (just west of I-170) in St. Louis County.  In addition, the signalized intersection at Page Industrial Blvd. will be reconstructed. A separate project will be completed to address pavement improvements in the area.

What are the existing issues along Route D?

  • Non-compliant Americans with Disabilities Act (ADA) ramps and entrances
  • Narrow sidewalks
  • Aging signals at Page Industrial Blvd.

Project Milestones

Complete
Preliminary Plans
October 2024
milestone_icon
Complete
Community Engagement Activities
Sept. 9 - Oct. 4, 2024
milestone_icon
In Progress
Right of Way Acquisitions
Spring 2025
milestone_icon
Not Started
Public Meeting
November 13, 2025; 4-6 p.m.

Overland Community Center
9225 Lackland Rd. 
Overland, MO 63114

This is an open-house style meeting.  Individuals my attend anytime between 4-6 p.m., view plans for the project and speak with team members.

milestone_icon
Not Started
Contract Awarded
March 2026
milestone_icon
Not Started
Construction Begins
April 2026
milestone_icon
Not Started
Construction Complete
Summer 2027
milestone_icon

Is MoDOT purchasing property from landowners?

MoDOT will need to purchase some property and/or obtain temporary easements in order to construct the additional sidewalks and ADA improvements.  A Right of Way representative will be contacting affected landowners to begin the acquisition process. 

How much will this project cost?

The cost of construction is estimated at $3 million.

How can I provide input on the project?

An interactive map and survey were available to stakeholders Sept. 9 - Oct. 4, 2024.  A public meeting will be held Nov. 13, 2025. The meeting will be held at the Overland Community Center, 9225 Lackland Rd., 63114.

This is an open-house style meeting.  Individuals my attend at any time between 4-6 p.m., view plans for the project and speak with team members.

 

Embed
Is Responsive
Embed Code

WHO TO CONTACT

Contact Photo
Photo of Tabitha Locke
Tabitha Locke
Title
Area Engineer -- North St. Louis County
Department
St. Louis District
Contact Info

Office: 314-453-1749
Email: tabitha.locke@modot.mo.gov 

Contact Photo
Photo of Daniel Savigeau
Daniel Savageau
Title
Project Manager, North St. Louis County
Contact Info

St. Louis District
Phone: 314-453-5089
Email: daniel.savageau@modot.mo.gov