Counties Impacted
Christian
Route Impacted
CC
Work Type
Intersection Improvements
Planning Phase

news Project Summary

The Route CC Intersection Improvements project will improve safety and traffic flow along Route CC and the 22nd Street intersection just west of U.S. Route 65 in Ozark.

Project Milestones

Complete
Public Hearing
Tuesday, April 29, 2025, from 4:30 p.m. - 6 p.m.
Sonrise Baptist Church, 3550 E State Hwy CC, Ozark
milestone_icon
Complete
Eastbound Route CC Bridge Rehabilitation Over U.S. Route 65 Construction Begins
July 2025
(During Construction, Eastbound Route CC Bridge will only be CLOSED for up to 30 days)
milestone_icon
Route CC & 22nd Street Intersection Improvements Construction
July 2026
milestone_icon
Route CC & 22nd Street Intersection Improvements Construction Completion
December 2026
milestone_icon
Route CC Widening between Fremont and 23rd Street Construction
Future Project
milestone_icon

crane Project Information

Current Project

  • Intersection improvements at Route CC and 22nd Street to improve safety and traffic flow

Traffic Impacts

  • Lane closures and traffic shifts on Route CC from Fremont Road to 22nd Street 
    • 22nd Street: nighttime lane closures
  • Businesses will have access during construction

Construction Beginning: July 2026

Construction Completion: December 2026

 

Completed

  • Eastbound Route CC bridge rehabilitation over U.S. Route 65, including dual left turn lanes from eastbound Route CC to northbound Route 65

Traffic Impacts

  • Eastbound Route CC bridge
    • Eastbound bridge CLOSED for up to 30 days with signed detours
    • Westbound bridge will remain open
    • Detour: Route J, southbound Route 65, Route 14/Jackson Street, northbound Route 65

Construction Beginning: July 2025

Construction Completion: August 2025

crane Project Information

Future Project

  • Widen Route CC to a 4-lane with raised medians from Fremont Road to 23rd Street
  • 10-foot wide shared-use path on the north side of Route CC
  • 5-foot wide sidewalk on the south side of Route CC

 

Estimated Total Cost of all 3 Projects: $15.9 million (Cost share with the City of Ozark and Ozarks Transportation Organization)

news NEWS RELEASES

Frequently Asked Questions:

Will there be any road closures during construction?

Intersection work may require occasional lane closures. However, one lane in each direction will be open throughout construction.

Will businesses maintain access during construction?

Residential and businesses will have access during construction.

Will the project affect residential or business access?

A 6-inch raised concrete median will be installed from 23rd Street to 22nd Street.

What type of pedestrian improvements will be constructed with this project?

The project includes new pedestrian accommodations on all corners of the Route CC and 22nd Street intersection. New pedestrian push‑buttons will be installed to provide “walk” signals at all four corners.

Webform
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.
Embed
Is Responsive
Embed Code

worker Project Contacts

Contact Photo
Beth Schaller Portrait
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info

Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Southwest Missouri Council of Governments: Barry, Christian, Dade, Dallas, Greene, Lawrence, Polk, Stone, Taney, & Webster Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120

 

Contact Photo
Ray Cook, Project Manager
Ray Cook
Title
Transportation Project Manager
Department
Design
Contact Info

Email: darrell.cook@modot.mo.gov
Phone: (417) 895-7644