Counties Impacted
Franklin
Route Impacted
MM
Work Type
Safety and Operational Improvements
In Progress

Project Summary

This project will provide pavement resurfacing, guardrail and sign upgrades, add shoulders, curve realignment (at Union Pacific Railroad), and improve box culverts on Route MM from Route T to Route 100 in Franklin County.

Project Milestones

Complete
Project Design
July 2023
milestone_icon
Complete
Project Advertised
April 2024
milestone_icon
In Progress
Contract Awarded
November 2024

NB West Contracting Team 

milestone_icon
In Progress
Construction Begins
Winter/Spring 2024
milestone_icon
In Progress
Construction Complete

October 1, 2025 

milestone_icon

COST OF PROJECT

$6.7 Million
 

IMPACTS TO TRAFFIC

Driving lanes will be open throughout the duration of the project, except for a period in spring/summer 2024 when a section of the roadway will be closed to thru traffic at the Union Pacific RR overpass for five to seven weeks. During this time, through traffic will be diverted to Route 100 as the designated detour.  Other short-term lane closures are anticipated at various locations and times.

What work has been completed?

 

What is happening currently in Spring 2025?

Most of the shoulder widening and asphalt resurfacing work was completed Fall 2024. The contractor will still be performing grading work later this Spring. There are two large box culverts where crews perform extension work and address erosion issues. Traffic has been reduced to one lane with a temporary traffic signal during the course of this work (March 2025) 

 

Project Contacts

Contact Photo
Jordan Dalaviras
Jordan Dalaviras
Title
Area Liaison, Franklin and Jefferson County
Department
St. Louis District
Contact Info

Phone: (314) 453-5021
E-mail: jordan.dalaviras@modot.mo.gov