Counties Impacted
Jasper
Route Impacted
43
M
Work Type
Bridge Rehabilitation
Planning Phase

Purpose and Need

These three bridges are being rehabilitated due to the poor condition of the bridge deck/driving surface.

Project Information

Contractor will remove the bridge deck/driving surface of these three bridges and replace them with a new, smoother, safer driving surface.

Project Milestorns

Complete
Virtual (online) Public Meeting
March 9-23, 2025
milestone_icon
Not Started
Project Out for Bid
April 18, 2025
milestone_icon
Not Started
Project Awarded
May 7, 2025
milestone_icon
Not Started
Construction Begins
Summer 2025
milestone_icon
Not Started
Project Completion
June 30, 2026
milestone_icon

NEWS RELEASES

Frequently Asked Questions

Will the bridges be closed during this project?

Yes, each abridge will be closed during construction. However, they will be closed one at a time. No two bridges will be closed at the same time.

Will there be signed detours?

Yes, there will be signed detours for each bridge. Maps showing the detour routes are posted above.

How long will each bridge be closed?

Route 43/North Fork Spring River up to 115 days

Route 43/Spring River up to 115 days

Route M/Duvall Creek up to 57 days

How do I ask a question about this project or leave feedback?

You may submit your question or comment about this project on the comment form below during the comment period between March 9 and March 23, 2025. You also may send an e-mail to swcr@modot.mo.gov or call (417) 895-7600.

Webform