Crews will be replacing the Route K/EE bridge over Interstate 70 beginning on Monday, May 1, 2023.
About the project
This project will remove and replace the Route K/EE bridge in Saline County. The existing bridge, which was constructed in 1961, is in poor condition and has reached the end of its service life.
Construction schedule
Construction will begin in the spring or summer of 2023.
Traffic impacts
This replacement will require the total closure of northbound and southbound Route K/EE over I-70 during this time. Additionally, I-70 will be reduced to one lane and diverted to the on and off ramps of Route EE/K beginning on Monday, May 1 at approximately 9 a.m. until Wednesday, May 3, at 6 am for bridge demolition. After the bridge removal, traffic on Route K/EE will have access to the I-70 ramps. The bridge will remain closed for the duration of the project. Eastbound and westbound I-70 traffic will be reduced to one lane at various times during the project. Motorists along Route K/EE will need to seek alternate routes during the closure.
Progress Pictures
News Releases
-
Route K/EE bridge over I-70 to be CLOSED for replacement beginning May 1- through September
SALINE COUNTY – Crews will be replacing the Route K/EE bridge over Interstate 70 beginning on Monday, May 1, and the project is scheduled to last until the end of September. This replacement will require the total closure of northbound and southbound...

Need More Information?
We're here to help. If you need additional information, you may contact MoDOT Kansas City Area Engineer Ben McCabe.
- Ben McCabe, MoDOT Area Engineer: Johnson, Lafayette, Pettis, and Saline Counties
Phone: 816.607.2097
Email: benjamin.mccabe@modot.mo.gov
- MoDOT Customer Service Line: 1-888-275-6636