Route 40 Bridge Rehabilitation over the Missouri River
Below are details, resources and news about the rehabilitation of the U.S. Route 40 bridge over the Missouri River in Boonville.
Project Details
When:
The project began on June 21, 2021, and was completed in December, 2021.
Cost:
The project was awarded to Capital Paving & Construction, LLC for the low bid of $1,262,640.83.
Work Taking Place:
Bridge rehabilitation. The existing bridge was constructed in 1995. This rehabilitation consisted of preventive maintenance to get the maximum service life out of the bridge. This rehabilitation also included guardrail replacements.
Project Milestones
On January 5, 2021, the Missouri Highways and Transportation Commission awarded the project to Capital Paving & Construction, LLC for the low bid of $1,262,640.83.
Work began on June 21, 2021.
Project News & Updates
-
Missouri River Bridge Rehabilitation Begins Next Week in Boonville
COOPER COUNTY – Work to rehabilitate the Missouri River Bridge on U.S. Route 40 in Boonville is scheduled to begin on Monday, June 21.
Route 40 will be open to traffic with a reduced speed limit and temporary striping to guide traffic through the work... -
CORRECTION: MoDOT Releases Details Regarding Route 40 Bridge Rehabilitation in Boonville
Editors: Information regarding the closure of the Katy Trail and Gov. Mike Parson’s $351 million Focus on Bridges program has been removed. There are no planned closures of the Katy Trail during this project. This project is not included in the Focus...

Stay Connected!
Check out facebook.com/modotcentral and @MODOT_Central on Twitter to follow us and know what's happening near you! You can also click the button below to subscribe to district news and have the information sent straight to your inbox!