Counties Impacted
Cooper
Completed

Rehabilitation of Cooper County Routes M & Z Bridges over I-70 (Complete)

Below are details, resources and news about the rehabilitation of the 60-year-old bridges on Cooper County Routes M & Z over Interstate 70, located approximately 10 and 15 miles west of Boonville, respectively. Both bridges reached a point where rehabilitation is necessary. 

 

Project Details

When: 

The project took place in 2022.

Cost: 

The contract amount is $1,650,249. 

Work Taking Place

Rehabilitation consisted of deck repair and a new concrete wearing surface will be applied, which improves the smoothness of the ride across the bridges.  The rehabilitation was necessary to extend the life and usability of both bridges. 

Project Milestones

Complete
Public Feedback Period
April 6-20, 2021
milestone_icon
Complete
Bid Awarded
April 6, 2022

The Missouri Highways and Transportation Commission awarded the contract for the project to Widel, Inc., which submitted the low bid of $1,650,249. 

milestone_icon
Complete
Preliminary Work Begins
August 22, 2022

The preliminary work allowed the contractor to complete the curb block outs for both bridges, in hopes to help accelerate work on both bridges in the project. 

milestone_icon
Complete
Route Z Bridge Rehabilitation
milestone_icon
Complete
Route M Bridge Rehabilitation
milestone_icon

Project News

Image
CD Social Media Icons

Stay Connected

Check out facebook.com/modotcentral and @MODOT_Central on Twitter to follow us and know what's happening near you! You can also click the button below to subscribe to district news and have the information sent straight to your inbox! 

Subscribe to email/text updates