Counties Impacted
Howard
Completed

Project Milestones

Complete
Project Awarded

At its regular meeting on October 4, 2019, the Missouri Highways and Transportation Commission (MHTC) awarded the contract for the project to Widel, Inc., which submitted the low bid of $508,678. 

milestone_icon
Complete
Construction Begins

Work to replace the bridge began on June 29, 2020.

milestone_icon
Complete
Work Complete

The new bridge was opened to traffic in September, 2020. 