Project Milestones
Complete
Project Awarded
At its regular meeting on October 4, 2019, the Missouri Highways and Transportation Commission (MHTC) awarded the contract for the project to Widel, Inc., which submitted the low bid of $508,678.
Complete
Construction Begins
Work to replace the bridge began on June 29, 2020.
Complete
Work Complete
The new bridge was opened to traffic in September, 2020.