Project Summary

The Crawford County Outer Road 44 bridge over the Little Bourbeuse River, east of Cuba, was built in 1966. Over the years, the bridge has begun to deteriorate and needs to be rehabilitated. The bridge will have a new deck, upgraded concrete barriers and new guardrail installed. 

Project Progress

Complete
Planning, Design, and Right of Way Acquisition Phase

A project to replace the bridge is currently being designed by engineers with the Missouri Department of Transportation. The estimated cost for this work is $835,000 – subject to change. 

milestone_icon
Complete
Public Outreach

A three-week public comment period starts Oct. 8, 2024. MoDOT plans to host an in person public meeting for this project in combination with 4 other upcoming bridge projects in the area. This meeting will take place on October 15, 2024 at the Bourbon Area Community Center located at 575 Elm St, Bourbon, MO 65441. 

 

Route J Bridge Replacement over Boone Creek in Crawford | Missouri Department of Transportation (modot.org)

Route C, Route FF, and Beamer Lane Bridge Rehabilitation over Interstate 44 in Crawford | Missouri Department of Transportation (modot.org)

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

The project was part of MoDOT's February 2025 letting when contractors submitted competitive bids. The Missouri Highways and Transportation Commission award the $579,282.50 contract as part of their March 2025 meeting to E & C Bridge LLC. 

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

After construction begins, the contractor will have approximately 70 calendar days to complete the project. At this time, construction is anticipated to start April 7, 2025, and be complete by June 6, 2025. Outer Road 44 over the Little Bourbeuse River will be closed for the duration of the work. Closing the bridge makes the road safer for our contractor and the drivers. 

milestone_icon

FREQUENTLY ASKED QUESTIONS

Why is MoDOT rehabilitating the bridge?

Built in 1966, the elements and travelers have taken their toll on the bridge deck. The deck has deteriorated to the point where it needs to be replaced, but the substructure is still in good condition. 

The bridge will be closed during construction and travelers will need to use an alternate route.  

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Crawford County OR 44 over Little Bourbeouse River Bridge Project on your inquiries.

Sign up for project-specific updates using the form below.

 

Webform