Update: Daviess County Route KK Bridge over Interstate 35 project to begin May 28

CAMERON, Mo. –After facing delays contractors from Capital Paving and Construction, working with the Missouri Department of Transportation, now plan to begin construction on the Daviess County Route KK bridge over Interstate 35 on Tuesday, May 28. The bridge will remain closed through early July.

Rehabilitation Schedule:

  • Clinton County
    • U.S. Route 69 bridge south of Cameron – NOW thru early June
  • Daviess County
    • Route KK bridge – May 28 thru mid-July
    • Route DD bridge - Late June thru early Sept.
    • Route B/N bridge – Mid-Aug. thru late Oct.
    • Route C bridge – Late Aug. thru early Nov.

During the bridge projects, the bridges will be closed. Motorists should follow signed detour routes.

Interstate traffic will also be affected. For safety reasons, no traffic will be permitted under the bridges during demolition. Interstate traffic will be narrowed to one lane in each direction and all traffic will be routed up and over the on and off ramps at the exit. Any reduction of lanes on I-35 will be completed during nighttime hours between 9 p.m. and 6 a.m.

All work and schedules are weather permitting. MoDOT encourages all motorists to slow down, buckle up, eliminate distractions and drive safely to ensure everyone is able to Arrive Alive.

Visit the project’s webpage to learn more about the plans for the new bridge and to sign up for project-specific updates via email at https://www.modot.org/clinton-and-daviess-county-bridge-deck-replacements-over-i-35

 

For more information on this and other MoDOT projects, call 1-888-ASK-MODOT (888-275-6636) or visit www.modot.org/northwest and view the online Traveler Information Map.In addition, MoDOT provides updated information on Twitter @MoDOTNorthwest and Facebook at www.facebook.com/MoDOTNWDistrict.

 

###