Project Status
Planning Phase
Route Impacted
U.S. Route 69

Project Milestones

Complete
Contractor Bids

The project will be let in January 2019 allowing contractors to submit competitive bids for the project.

Complete
Contract Awarded

The Missouri Highways and Transportation Commission awarded the project contract to Capital Paving and Construction during their February 2019 meeting.

In Progress
Contractor May Begin Work

The current notice to proceed date will be March 19, 2019. Construction is scheduled to begin April 8 on the U.S. Route 69 bridge south of Cameron.

 

Rehabilitation Schedule:

  • Clinton County
    • U.S. Route 69 bridge south of Cameron – Completed  
  • Daviess County
    • Route KK bridge – Completed
    • Route C bridge – July 8 through Sept. 6   
    • Route DD bridge – Sept. 9 through Nov.
    • Route B/N bridge – Sept. 16 through Nov.
       

 

Not Started
Completion

The contracted completion date is November 1, 2019, though the contractor may finish the job before that date if factors allow.

Project Information

Contractors will replace the decks of Clinton County U.S. Route 69 and Daviess County Routes KK, DD, C and B bridges over I-35. During construction of each bridge will close and traffic will be directed over the signed detour routes shown below.

Project Press Releases

  • Delayed: Daviess County Route C Bridge to reopen

    09/05/2019

    CAMERON, Mo. – Contractors from Capital Paving and Construction, working with the Missouri Department of Transportation, are now planning to reopen the Route C bridge (Pattonsburg) over Interstate 35 to traffic on Monday, Sept. 9 and close the Route...

  • Update: Daviess County Route C Bridge to reopen

    09/03/2019

    CAMERON, Mo. – Contractors from Capital Paving and Construction, working with the Missouri Department of Transportation, are scheduled to reopen the Route C bridge (Pattonsburg) over Interstate 35 to traffic on Friday, Sept. 6, weather permitting....

  • Update: Daviess County Route KK Bridge over Interstate 35 OPEN

    07/26/2019

    CAMERON, Mo. – Contractors from Capital Paving and Construction, working with the Missouri Department of Transportation, completed a rehabilitation project on the Daviess County Route KK Bridge over Interstate 35 yesterday afternoon.

    The Route KK...

Frequently Asked Questions

 

Q: Why is MoDOT closing the road during construction?

  • Closing the bridge saves taxpayer money by allowing the contractor to work more efficiently and will result in a shorter construction period. The bridge on and off ramps will remain open during construction.

Q: Who can I contact if I have further questions?

Q: How can I stay updated on the project's progress?

  • Sign up for project-specific updates below:
Webform
Contact Form
*
*
*
*