Project Update:

Route 65 Widening/Evans Road Bridge Projects

Update for Week of June 24

  • Work progressing on Evans Road Bridge
  • Nighttime lane closings on Route 65 for paving work

Work Scheduled:  

  • Building and paving pavement connections to Evans Road bridge
  • Pouring concrete for bridge walls on Evans Road bridge late in week
  • Laying asphalt in areas on northbound and southbound Route to correct "crown" of road
  • Pouring concrete for new bridge deck/driving surface on widened portion of Farmer's Branch bridge

Traffic Impacts:

  • Nighttime lane closings on Route 65. Work hours: 8 p.m. to 6 a.m.
  • Crews and equipment close to traffic during daytime hours

(Weather or construction delays could alter the work schedule.) 



Project Summary:

  • Widen Route 65 to six lanes — three lanes in each direction — between a point south of Evans Road and Christian County Routes CC/J  to continue the progress to six lane Route 65 south to Ozark
  • Widen and rehabilitate southbound Route 65 bridge over Farmer’s Branch south of Evans Road to accommodate new lanes
  • Rehabilitate Evans Road bridge over Route 65 (Evans Road bridge over Route 65 CLOSED during the project until late July 2019) 
  • Total Project Cost: $10.2 million
  • Overall Completion Date: August 2019 
  • Project web site

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District: 
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
 www.ozarkstraffic.com)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.