MoDOT TRAFFIC ALERT: Westbound I-44 Traffic Shift in Springfield Begins Tuesday night, May 27

Where: Westbound I-44 left lane traffic shifted to eastbound I-44 between U.S. Route 65 and Glenstone Avenue in Springfield

When: Beginning Tuesday Night, May 27

What: Contractor crews will begin to shift westbound I-44 traffic to the south at 8 p.m., Tuesday night, May 27, as crews begin to work in the westbound lanes of I-44 as part of the Forward 44: Springfield Improvements in Greene County project. The left lane of westbound I-44 will shift to the north side of eastbound I-44. Eastbound I-44 and the left lane of westbound I-44 will be in a head-to-head configuration with a median separating the two directions of traffic.

Traffic Impacts:

  • Westbound I-44 left-lane traffic shifted to the north side of eastbound I-44 between U.S. Route 65 and Glenstone Avenue
  • Eastbound I-44 and the left lane of westbound I-44 will be in a head-to-head configuration with a median separating the two directions of traffic
  • Eastbound I-44 is Open in two 12-foot lanes
  • Westbound I-44 is Open to two 12-foot lanes
  • No signed detours; drivers are urged to find alternate routes
  • Signs and message boards will alert drivers to work zones and inform the public when there are reduced speeds and traffic delays
  • Check MoDOT’s Traveler Information Map for road closures/traffic impacts

Weather and/or construction delays will alter the work schedule.

Project Summary:

  • Widening I-44 to 6 lanes between Missouri Route 13 (Kansas Expressway) and U.S. Route 65
  • Replace the following bridges carrying I-44 over city streets:
    • Broadway Avenue Bridge
    • Grant Avenue Bridge
    • National Avenue Bridge
  • Build a pedestrian underpass and trail improvements east of Grant Avenue
  • Resurface I-44 between west of Missouri Route 266 (Chestnut Expressway) and U.S. Route 160 (West Bypass)
  • Build a sound wall south of I-44 from the National Avenue bridge west, approximately 2,550 feet

Contractor: Capital Paving & Construction LLC, Jefferson City

The awarded construction cost is $70.7 million, including $13.4 million in General Revenue funds provided by the General Assembly and the Governor’s Office.

To get project updates or sign up for project emails, visit https://www.modot.org/projects/forward-44-springfield-improvements.

The project is scheduled for completion in May 2027.

END

For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

Follow MoDOT's Southwest District:
Facebook | X | Instagram |YouTube

Take the Challenge! Buckle Up/Phone Down

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Media Inquiries
Regan Mitchell, Senior Communications Specialist
Regan Mitchell
Senior Communications Specialist
Southwest District

Missouri Department of Transportation

3025 East Kearney, Springfield, MO 65803

Phone: (417) 895-7600

Email: swcr@modot.mo.gov

website: www.modot.org/sw

Real Time Traffic

Monitor real time traffic with our online traffic map.