Project Summary

The I-44 Corridor Upgrades in Greene County include pavement rebuild, lane widening, bridge replacement, a sound wall, pedestrian underpass, and resurfacing along the I-44 Corridor in the Springfield area to improve capacity between Kansas Expressway and U.S. Route 65. This project is part of the Forward 44 Planning Study.

Project Milestones

Public Meeting
Tuesday, March 19, 2024, from 4:30 p.m. - 6 p.m.
Crossway Baptist Church, 2900 N Barnes Ave, Springfield
milestone_icon
Public Meeting
Tuesday, February 2025, from 4:30 p.m. - 6 p.m.
Crossway Baptist Church, 2900 N Barnes Ave, Springfield
milestone_icon
I-44 Widening Construction 2025-2027
Widening I-44 between Kansas Expressway and Route 65
Resurface I-44 west of Route 266 and east of U.S. Route 160
I-44 Sound Wall Construction
Pedestrian Underpass east of Grant Avenue
milestone_icon

Project Information

  • Replace pavement and widen I-44 to 6 lanes between Missouri Route 13 (Kansas Expressway) and U.S. Route 65
  • Replace the following bridges carrying I-44 over city streets:
    • Broadway Avenue Bridge
    • Grant Avenue Bridge
    • National Avenue Bridge
  • Build a pedestrian underpass and trail improvements east of Grant Avenue
  • Resurface I-44 between west of Missouri Route 266 (Chestnut Expressway) and east of U.S. Route 160 (West Bypass)
  • Build a sound wall south of I-44 from the National Avenue bridge west, approximately 2,550 feet

Traffic Impacts

  • Narrowed lanes, traffic shifts on I-44
  • I-44 will maintain two lanes of traffic in each direction, except for short-duration closures during nighttime hours
  • I-44 ramp closures
  • Road and bridge closures for the following locations:
    • Broadway Avenue closed up to 140 days
    • Grant Avenue closed up to 140 days
    • National Avenue closed up to 140 days
  • During higher traffic volume, drivers can expect delays

NEWS RELEASES

Frequently Asked Questions:

When will the road closures take place?

Construction is scheduled to begin in 2025, and finish May 2027.  An exact schedule will not be available until a contractor is awarded the projects.  MoDOT encourages people to sign up for automated email alerts to receive active construction information.

Will Broadway, Grant and National be closed at the same time?

To accommodate traffic flow across I-44, at least one of these roads will be open at all times.  Traffic will be expected to use the open road, as well as Kansas Expressway and Glenstone Avenue.

Why are there not more sound walls being built?

A sound study is done whenever MoDOT adds through lanes, a new road or changes the alignment of a roadway.  We can only build walls in locations where all criteria are met.  Additional information on the noise policy can be found here.

What type of pedestrian improvements will be constructed with this project?

Through a financial partnership with the City of Springfield and Greene County, a pedestrian underpass is being constructed to allow pedestrians to cross under I-44 east of Grant Avenue.  A shared-use path will be constructed from an existing trail south of I-44 to Norton Road on the north side of I-44. 

Is MoDOT purchasing property from landowners?

Acquiring property for the pedestrian underpass has been completed.  Additional information for the acquisition process can be found here.

How can I learn more about the Kansas Expressway (Route 13) Interchange project?

The Route 13 Interchange Improvements are not currently included with the Forward 44: Springfield Impovements project, as they are part of the Forward 44: Southwest I-44 Improvements Project. For more information, click on the link.

Webform
Embed
Is Responsive
Embed Code

Project Contacts

Contact Photo
Beth Schaller
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info
Ozarks Transportation Organization &
Southwest Missouri Council of Governments Areas:
Dallas, Polk, Webster, Greene, Dade, Lawrence,
Christian, Barry, Stone and Taney Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Contact Photo
Kristi Bachman
Kristi Bachman
Title
Forward 44 Southwest Project Director
Department
Southwest District
Contact Info

Email: Kristi.Bachman@modot.mo.gov
Phone: (417) 834-7171
Fax: (417) 895-7664

Contact Photo
Brad Gripka
Brad Gripka
Title
Springfield Resident Engineer
Department
Construction and Materials
Contact Info

Southwest District

Email: Donald.Gripka@modot.mo.gov
Phone: (417) 895-6720