Andrew County
Interstate 29 – Resurfacing from U.S. Route 59 north of the Nodaway River to Business 71 north of St. Joseph through July 2025. (Contractor: Herzog Contracting Corp.).
Atchison County
Route 111 – Culvert Replacement at Kettle Avenue, April 23.
Buchanan County
Route DD – CLOSED at the Jenkins Creek Bridge near Gower for a bridge deck replacement project through mid-May. (Contractor: Capital Paving & Construction, LLC). https://www.modot.org/projects/route-b-route-dd-and-route-h-bridge-rehabilitation-andrew-and-buchanan.
Caldwell County
Route D – CLOSED for a bridge replacement project at the Shoal Creek Bridge through early August 2025 (Contractor: Cale Seymour Construction, LLC). https://www.modot.org/route-d-bridge-replacement-caldwell.
Route W – Bridge rehabilitation project at the East Sheep Creek Bridge, April 18-22. The roadway will be narrowed to one lane with flaggers directing motorists through the work zone. (Contractor: Capital Paving & Construction, LLC). *2
Carroll County
Route J - CLOSED at the Bridge Creek Bridge for a bridge replacement project through May 2025. (Capital-Horner & Shifrin).*1
Chariton County
Route D – CLOSED at the Mussel Fork Creek Bridge for a bridge replacement project through July 2025. (Capital-Horner & Shifrin).*1
Route W – Resurfacing project to Missouri Route 3 in Randolph County, April 21-26. The roadway will be narrowed to one lane with flaggers directing motorists through the work zone. (Contractor: Capital Paving & Construction, LLC).
Route C – Resurfacing project April 23-30. The roadway will be narrowed to one lane with flaggers directing motorists through the work zone. (Contractor: Capital Paving & Construction, LLC).
Route ZZ – Resurfacing project April 26-May 5. The roadway will be narrowed to one lane with flaggers directing motorists through the work zone. (Contractor: Capital Paving & Construction, LLC).
DeKalb County
Route 6 – Resurfacing from west of Maysville to Route 31 through April 2025. (Contractor: Herzog Contracting Corp.).
Holt County
I-29 – Resurfacing from U.S. Route 59 north of the Nodaway River to Business 71 north of St. Joseph through July 2025. (Contractor: Herzog Contracting Corp.).
I-29 (northbound) – Slide repair south of Route W near Corning through April (Contractor: C.P. Excavating, LLC).
Route 120 – CLOSED for pothole patching from U.S. Route 59 to Route B, April 21, 7 a.m. to 3:30 p.m.
Route 111 – Pothole patching from the north city limits of Forest City to Liberty Road, April 22-24.
Linn County
U.S. Route 36 – Concrete replacement eastbound driving lane from Route F to Route 5, April 21-25.
Route TT – CLOSED in one mile increments for pothole patching from U.S. Route 36 to Route 139 in Chartiton County, April 21-25, 7 a.m. to 4 p.m. daily.
Route ZZ – Resurfacing project, April 26-May 5. The roadway will be narrowed to one lane with flaggers directing motorists through the work zone,
Livingston County
U.S. Route 65 – Resurfacing project, April 21-25. Crews will be repairing entrances and curbs in Chillicothe from Business U.S. 36 working north to Second Street. (Contractor: Capital Paving & Construction, LLC).
Nodaway County
Route NN – CLOSED until further notice at the Platte River Bridge west of Parnell due to significant bridge deterioration. This bridge is scheduled for the March 2025 contractor letting through the Statewide Transportation Improvement Program. https://www.modot.org/route-nn-bridge-replacement-nodaway.
Route C – Culvert replacement at Catalina Road, April 21, 8 a.m. to 3 p.m. There will be no access to/from Catalina Road.
Route B – CLOSED for a culvert replacement from Fortune Road to Glacier Road, April 22, 8 a.m. to 3 p.m.
Route FF – CLOSED for a culvert replacement from 130th Road to 140th Road, April 23, 8 a.m. to 3 p.m.
Route 46 – Culvert replacement at Y Avenue, April 24, 8 a.m. to 3 p.m. There will be no access to/from Y Avenue.
Putnam County
U.S. Route 136 – CLOSED in various locations for multiple culvert replacements from Route 139 to Route U, April 21-25, 6 a.m. to 5 p.m. daily.
---
*1 This bridge is part of the NWBB (Northwest Bridge Bundle) program. The design-build team is Capital-Horner &Shifrin. More info: NWBB program web page.