TRAFFIC ALERT: Expect Traffic Delays on I-44 at Route K/PP (Exit 61) in Greene Co. July 16-17

Where: I-44 at Greene County Route K/PP bridge (Exit 61) west of Springfield where new bridge is being constructed

When: Between 7 p.m., Tuesday, July 16 and 7 a.m., Wednesday, July 17

What: I-44 traffic diverted up and over the ramps in both directions at Exit 61 to allow contractor to set bridge girders for new bridge

Traffic Impacts:

  • All I-44 traffic in both directions will be diverted up and over the ramps at Exit 61 while contractor crews set bridge girders
  • Drivers should expect delays while crews are working
  • After girders are in place, drivers may experience occasional nighttime lane closures, traffic delays while contractor crews do additional work on the bridge deck/driving surface over I-44
  • Signs and message boards will alert drivers approaching the work zone
  • Drivers encouraged to find alternate routes around the work zone
  • Check MoDOT’s Traveler Information Map for road closings/traffic impacts

Weather and/or scheduling conflicts could alter the work schedule.

Details: This work is part of a three-year project to improve 25 bridges within 15 miles of I-44 across the Southwest District. Of the 25 bridges in the project, known as the I-44 Corridor Bridge Bundle, seven (7) are mainline I-44 bridges, five (5) are I-44 overpass bridges and the remaining bridges are on adjacent routes over various features. Sixteen (16) bridges will be replaced and nine (9) bridges will receive major rehabilitation work.

More information about this project can be found on the project website – I-44 Corridor Bridge Bundle.

Project Details:

  • Prime Contractor – The ESS Team
    • Emery Sapp & Sons, Inc. – Columbia
    • Parsons Transportation Group, Inc. – St. Louis
  • Total Project Cost: $43.2 million
  • Contract Completion Date: September 30, 2024

The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.

 

 

For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

Follow MoDOT's Southwest District: Facebook | X | Instagram |YouTube

Take the Challenge! Buckle Up/Phone Down

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.