Replace or rehabilitate bridges rated as in poor or fair condition along I-44 and various other routes within a 15 mile radius of the interstate across the Southwest District.

Counties Impacted
Dallas
Greene
Jasper
Lawrence
Webster
Project Status
Planning Phase

Project Goals:

  1. Deliver a safe project within the programmed budget of $38.055 million
  2. Maximize the number of locations to be addressed while providing quality structures
  3. Use innovation to reduce delay and minimize impacts to the public
  4. Deliver the project utilizing a diverse work force
  5. Complete the project on or before November 1, 2024

Tentative Procurement Schedule:

  • Project Advertisement -- May 2021
  • Request for Qualifications/Industry Meeting -- June 2021
  • Statement of Qualification Shortlist -- July 2021
  • Request for Proposal -- August 2021
  • Award -- January 2022

For more information, contact Project Director, Laurel McKean at laurel.mckean@modot.mo.gov or (417) 818-9043.