MoDOT: Interchange Project at Route 60/Route 125 in Rogersville

Beginning the Week of March 13

Rogersville, Greene County – Drivers can expect lane and median crossover closures, narrow lanes and traffic shifts on U.S. Route 60 and lane and road closures on Missouri Route 125 in Rogersville when contractor crews build a new interchange at U.S. Route 60/Route 125 intersection beginning the week of March 13, the Missouri Department of Transportation said.

Here’s a look at the project:

  • Build interchange at U.S. Route 60/Route 125 intersection
  • Build interchange ramps for safe access between U.S. Route 60 and Route 125
  • Build outer road from Missouri Route 125 to Farm Road 229 and Farm Road 243

Traffic Impacts:

  • All Stages
    • Narrowed lanes and traffic shifts on Route 60
    • Crews and equipment close to traffic in areas
    • Signs and message boards will alert drivers approaching the work zone
    • Drivers should look for alternate route
  • Stage 1 (March 13 – August 2023)
    • Farm Road 229 median crossover CLOSED permanently
  • Stage 2 (July – September 2023)
    • Expect significant traffic delays at the Route 60/Route 125 signal
    • Drivers are encouraged to look for alternate routes
  • Stage 3 (September 2023 – May 2024)
    • Expect significant traffic delays at the Route 60/Route 125 signal
    • Drivers are encouraged to look for alternate routes
  • Stage 4 (April – May 2024)
    • Route 60 left turn lanes onto Route 125 CLOSED
    • Route 125 traffic will not be allowed to turn left onto Route 60
    • Route 125 traffic will be allowed to turn right onto Route 60
    • Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
    • Signed detour used during this stage
  • Stage 5 (May – November 2024)
    • Route 125 CLOSED at Route 60
    • Route 60 will have no access to Route 125
    • Route 125 will have no access to Route 60
    • Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
    • Signed detour used during this stage

Weather and/or construction delays will alter the work schedule.

Project information:

 

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram | YouTube)

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest