Counties Impacted
Greene
Project Status
Planning Phase

Project Timeline

2018-2019
Conduct environmental studies to determine impacts
2019
Preliminary project design work begins
Summer/Fall 2019
Public meeting to show preliminary project design
2020
Secure land needed for project
2021
Final project design work completed
2022-2023
Construction of new interchange and outer roads

Project Facts:

  • Build new bridge to carry Route 60 over Route 125
  • Build interchange ramps for safe access between Route 60 and Route 125
  • Build outer roads in areas
  • Connect business entrances to new outer roads
  • Greene County Farm Road 229 connection to Route 60 removed
  • Tentative construction schedule: 2022-2023
  • Estimated construction cost: $17.2¬†million