Rogersville, Greene County – The public is invited to learn more about the final project design and traffic impacts during construction of a new interchange at U.S. Route 60 and Missouri Route 125 in Rogersville, the Missouri Department of Transportation said.

The public meeting is scheduled for 4:30-6 p.m. on Thursday, January 19, at Logan-Rogersville High School, 300 N. Missouri Boulevard (Route 125 north of U.S. Route 60). The meeting will be come-and-go with NO FORMAL PRESENTATION planned. Those who attend can come at any time between 4:30 and 6 p.m.

Anyone unable to attend the in-person meeting can view the same exhibits at an online public meeting available at www.modot.org/southwest.

The project will build an interchange at the U.S. Route 60/Route 125 intersection and removing the existing traffic signal. Construction of the project will begin in 2023 with completion in 2024.

Here’s a look at the project:

  • Build interchange at U.S. Route 60/Route 125 intersection
  • Build interchange ramps for safe access between U.S. Route 60 and Route 125
  • Build outer road from Missouri Route 125 to Farm Road 229 and Farm Road 243

Traffic Impacts:

  • All Stages
    • Narrowed lanes and traffic shifts on U.S. Route 60
    • Crews and equipment close to traffic in areas
    • Signs and message boards will alert drivers approaching the work zone
    • Drivers should look for alternate route
  • Stage 1
    • Farm Road 229 median crossover CLOSED permanently
  • Stage 2 (approximately 1 month)
    • U.S. Route 60 left turn lanes onto Route 125 CLOSED
    • U.S. Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
    • Signed detour used during this stage
  • Stage 3 (approximately 7 months)
    • No impacts to traffic
  • Stage 4 (approximately 3 months)
    • U.S. Route 60 left turn lanes onto Route 125 CLOSED
    • Route 125 traffic will not be allowed to turn left onto U.S. Route 60
    • Route 125 traffic will be allowed to turn right onto U.S. Route 60
    • U.S. Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
    • Signed Detour used during this stage
  • Stage 5 (approximately 2.5 months)
    • Route 125 CLOSED at U.S. Route 60
    • U.S. Route 60 will have no access to Route 125
    • Route 125 will have no access to U.S. Route 60
    • U.S. Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
    • Signed Detour used during this stage

Weather and/or construction delays will alter the work schedule.

Project information:

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram | YouTube)

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest