Franklin County, MO -- MoDOT crews are rescheduling work on Missouri Route 30 ramps over Interstate 44 in St. Clair, MO due to material availability issues with asphalt. The work, which was scheduled to begin on Monday, March 14 has been pushed back to Monday, March 21.
When the work begins, motorists will experience ramp and lane closures as crews rehabilitate and redeck bridges over I-44 on Routes 30 and 47. The Route 30 interchange ramps, which are in the first phase of the project, will accommodate increased traffic from the Route 47 interchange when lane closures begin on April 6. Workers will remove existing shoulders and new asphalt will be put in its place on Route 30 ramps. Various ramps will be closed between 6 a.m. and 6 p.m.
For more information and to stay up-to-date on this project, go to https://www.modot.org/node/25277.