Patching and Bridge Work Continues for Routes in Lincoln County

MACON - Weather permitting, MoDOT will be doing the following work on routes in Lincoln County. Please see the dates and locations below.

Lincoln County Route KK - Aug. 26-29,  the road will be reduced to one lane at the U.S. 61 bridge for bridge work.  The work will be completed between 8:00 a.m. and 4:00 p.m. each day. There will be a 10 foot width restriction in place during this time.

Lincoln County Route UU - Aug. 26-27,  the road will be reduced to one lane at various locations from Lincoln County Ruote E to Lincoln County Route Z for patching operations.  The work will be completed between 7:00 a.m. and 4:00 p.m. each day. There will be an 11 foot width restriction in place during this time.

Lincoln County Route K - Aug. 28-29,  the road will be reduced to one lane at various locations from U.S. Route 61 to where state maintenance ends for patching operations.  The work will be completed between 7:00 a.m. and 4:00 p.m. each day. There will be an 11 foot width restriction in place during this time.

U.S. Route 61 Outer Road - Sept. 3,  the road will be reduced to one lane from old U.S. Route 61 to where state maintenance ends for patching operations.  The work will be completed between 7:00 a.m. and 4:00 p.m. each day. There will be a 10 foot width restriction in place during this time.

Davis Road - Sept. 4,  the road will be reduced to one lane from Lincoln County Route KK to where state maintenance ends for patching operations.  The work will be completed between 7:00 a.m. and 4:00 p.m. each day. There will be a 10 foot width restriction in place during this time.

John Deere Drive - Sept. 5,  the road will be reduced to one lane from South Lincoln Drive to Lincoln County Route C for patching operations.  The work will be completed between 7:00 a.m. and 4:00 p.m. each day. There will be a 10 foot width restriction in place during this time.

U.S. Route 61 west Outer Road - Sept. 6,  the road will be reduced to one lane from U.S. 61 to where state maintenance ends for patching operations.  The work will be completed between 7:00 a.m. and 4:00 p.m. each day. There will be a 10 foot width restriction in place during this time.

Please use caution if you will be traveling through these areas and remember to obey all work zone signs and personnel, and put down your cell phone to help eliminate distractions.

Again, this work is weather dependent and could be rescheduled or delayed. For more information, contact MoDOT's Customer Service Center toll-free at 1-888-ASK MoDOT (275-6636). All roadwork is posted on the traveler information map. You can also visit us online at www.modot.org/northeast.