MoDOT Project Update:

Route 65 Widening/Evans Road Bridge Projects Week of August 19
  • Nighttime lane closings on Route 65 for guardrail/guard cable work 

Work Scheduled:

  • Installing new guardrail/guard cable
  • Building approach pavement to existing southbound Route 65 bridge at Farmer Branch 

Traffic Impacts:

  • Nighttime lane closings on Route 65 between Springfield Lake bridge and Christian County Routes CC/J. Work hours: 8 p.m. to 6 a.m.
  • Equipment moving in and out of work areas, especially during nighttime hours
  • Southbound Route 65 traffic shifted to left at Farmer Branch. Two lanes remain open across bridge.
  • Southbound Route 65 speed limit reduced to 55 mph
  • EARLY HEADS UP: New lanes of Route 65 scheduled to open following Labor Day holiday 

(Weather and/or construction delays will alter the work schedule.) 

Here’s a look at the Route 65/Evans Road Bridge project:

  • Widen Route 65 to six lanes, three lanes in each direction, between a point south of Evans Road and Christian County Routes CC/J  to continue the progress to six lane Route 65 south to Ozark
  • Widen and rehabilitate southbound Route 65 bridge over Farmer Branch south of Evans Road to accommodate new lanes
  • Rehabilitate Evans Road bridge over Route 65 — COMPLETE
  • Prime contractor is Millstone Weber, LLC of St. Charles
  • Estimated total project cost is $10.2 million
  • Project scheduled for completion late September 2019
  • Project website  

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest