Project Summary

The Missouri Route 5 bridge over Bear Creek in Howard County, in Glasgow, is in need of replacement. During its life, the bridge’s rails were upgraded and driving surface improvements were made, but no major structural work has been completed. The structure was built in 1930 and both the deck and superstructure are in poor condition. Plans for the new bridge include improvements that will enhance safety, drivability, and traffic flow.

 

Project Details

When: 

This project will most likely begin in 2025 and be complete in approximately four months. Must be complete by Dec. 1 2025.

Cost: 

The estimated cost for the project, including construction and engineering is $3.9 million. 

Work Taking Place

The bridge will be completely replaced. The project is currently scheduled to be part of MoDOT's September 2024 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their October 2024 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

Traffic Impact:

The roadway is expected to remain open during construction, though some lane closures with narrowed lanes may be necessary.

Project Progress

Complete
Planning and Design Phase

The Missouri Department of Transportation designed functionality and safety improvements, including a wider bridge, pedestrian upgrades and updated bridge rails.

The estimated cost for these improvements, including construction and engineering, is $3.9 million. This cost may change.

milestone_icon
Complete
Public Meeting

Comment period: Jan. 30-Feb. 13, 2024

Public Meeting

A public open house will be held Jan. 30, from 4:30 to 6 p.m. at the American Legion at 705 Washington St. in Glasgow. There will be no formal presentation, so attendees may come and go anytime during the open house. Exhibits will outline the work being planned and the timing of construction.

The public is invited to provide comments and ask questions of the project team in person at the meeting, online or by mail by Feb 13. Mailed comments should be postmarked on or before Feb 14 and addressed to:

Howard County Missouri Route 5 Bear Creek Bridge Project
1511 Missouri Boulevard
Jefferson City, MO 65102

Meeting Exhibits

At the link below, find all available exhibits regarding the new bridge. Comments are accepted Jan. 30-Feb 13.

 

milestone_icon
Complete
Project Redesign

As a result of feedback from the Jan. 30, 2024, public meeting and subsequent open comment period, the proposed design for the Route 5 bridge has been modified to include a barrier between the pedestrian walkway and the driving lane. View the new design below in "Updated Bridge Design."

milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's September 2024 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their October 2024 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

The roadway is expected to remain open during construction, though some lane closures with narrowed lanes may be necessary.

milestone_icon

Project News and Updates

Project Materials

Webform
Have Project Questions or Feedback? Use the form below to share your questions, thoughts and comments.
*
*
*

Your email address shared here will not be used for any purpose other than communicating about this project.

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the Bridge?

The existing Route 5 bridge over Bear Creek was built in 1930, is currently narrower than the existing road, and the deck and barriers are showing signs it is nearing the end of its life cycle. The new structure will be up to current standards and improve the drivability and safety for motorists.

How will the construction affect traffic?

The contractor will stage lane closures on the bridge so one lane of traffic is maintained through the completion of the project.

What if I have further questions?

Questions about the project may be directed to CDCR@modot.mo.gov or by phone at 888 ASK MODOT (1-888-275-6636). Please reference the Howard County Route 5 Bear Creek Bridge project.

How can I stay updated on the projects progress?

Use the form above to sign up for project-specific updates. As the project moves into the construction phase and a schedule is known, updates will be provided on MoDOT's Central District on social media.