Counties Impacted
Washington
Route Impacted
47
Work Type
Bridge Rehabilitation
Highway Feature
Mill Creek
Planning Phase

Project Summary

The Missouri Route 47 bridge over Mill Creek in Washington County, north of Potosi, was constructed in 1965, is narrow, and the deck is in poor condition. A project is currently in the planning and design stage that will replace the current bridge deck with a wider one, bring the bridge rails up to current safety standards, and install new guardrail at the ends of the bridge. These improvements will enhance safety, drivability, and traffic flow.

Project Progress

In Progress
Planning, Design, and Right of Way Acquisition Phase

The Missouri Department of Transportation is currently designing functionality and safety improvements, including increasing the bridge width from 24 to 26 feet with a new deck, installing new rail on the bridge and installing new guardrail at bridge ends.

As of July 17, 2024, the estimated cost for these improvements, including construction and engineering, is $930,000. This cost is subject to change.

milestone_icon
Complete
Public Input

Comment period: July 25 – Aug. 15, 2024

During the three-week comment period that runs July 25 – Aug. 15, 2024, the community and interested parties have multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts. 

  1. In person: An open-house style public meeting is being held Thursday, Aug. 1, 2024, from 4:30 to 6 p.m., at Washington County Library (235 E High St, Potosi, MO 63664). The project team will be on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.  
  2. Online: All meeting exhibits will be available on this website and feedback will be accepted through Aug. 15, 2024, using the online form below.  
  3. By email:  Send your comments by Aug. 15, 2024, to CDCR@modot.mo.gov with the subject line: Washington County Route 47 Mill Creek Bridge Project
  4. By traditional mail: Comments may be mailed (postmarked by Aug. 15, 2024) to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109. Please reference Washington County Route 47 Mill Creek Bridge Project.
milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's January 2025 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their February 2025 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

At this time, construction is anticipated to begin in summer 2025 and be complete by Dec. 1, 2025. The current plan will close Route 47 during the construction of the new bridge for up to 110 calendar days and a signed detour will be in place using Routes 67, 8, and 21. 

milestone_icon

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge?

The existing Route 47 bridge over Mill Creek was built in 1965, and the deck needs to be replaced.  The bridge width, bridge rail, and guardrail need to be upgraded. The deck is in poor condition, but the substructure is in good condition. The new bridge deck and rail will improve the drivability and safety for motorists.

The current plan will close the bridge to all traffic through the completion of the project up to 110 calendar days. A signed detour will be posted over Routes 67, 8, and 21. 

What if I have further questions?

You may email CDCR@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Washington County Missouri Route 47 Mill Creek Bridge Project on your inquiries.

How can I stay updated on the project’s progress?

Sign up for project-specific updates using the form below.

Project Documents

Webform
Sign Up for Project Updates via Email
*
*