Counties Impacted
Boone
Route Impacted
151
22
124
Work Type
Roundabout Construction
Planning Phase

Project Summary

Beginning as early as June 2024, the intersection where Route 22 meets Routes 124 and 151 will be reconstructed into a roundabout.

The intersection of Missouri Routes 22, 124, and 151 in Centralia needs improvements. The existing four-way intersection creates less-than-optimal safety conditions for traffic. By installing a roundabout, the potential impact points for crashes, especially t-bone crashes, is greatly reduced, lowering the chance of a serious or fatal crash. The plans include improvements that will enhance safety, drivability, and traffic flow. The project is expected to be finished by 2025. 

 

Project Details

When: 

This project is scheduled to begin in the summer of 2024, and be complete by 2025. 

Cost: 

The estimated construction cost for the project is $1.1 million. 

Work Taking Place

The project plans include constructing a roundabout at the intersection of the Missouri Routes 22, 124, and 151. The proposed intersection layout will improve traffic flow and safety at the intersection.

Traffic Impact:

Route 151 will be temporarily closed to construct the north portion of the roundabout and will have a signed detour. Routes 22 and 124 will be staged to construct the remaining portions of the roundabout and at least one lane will remain open.

Project Progress

Complete
Planning and Design Phase

A project to construct a roundabout at the intersection of MO Routes 22, 124, and 151 is currently being designed by the Missouri Department of Transportation. The total construction cost for this project is $1.1 million. This cost may change.

milestone_icon
Complete
Public Input
Thursday, January 18, 2024

A public informational open-house was held Jan. 18, 2024, from 4:30 – 6 p.m., at Centralia City Hall Council Chambers. Exhibits outlined the work being planned and the road changes to be used during construction.

The public is invited to leave comments and questions for the project team, either in person, online or by mail. Mailed comments should be postmarked on or before Jan. 31 and addressed to:

Boone County Missouri Route 22 Roundabout Project

1511 Missouri Boulevard

Jefferson City, MO 65102

milestone_icon
In Progress
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's May 2024 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their June 2024 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

At this time, construction is anticipated to begin in the summer of 2024 and be completed by 2025. Work will be staged and Route 151 will be temporarily closed. Some additional lane closures may be necessary and some width and turning restrictions may be in place throughout the project.

milestone_icon

Project News and Updates

Project Overview

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the Route 22 Intersection?

The existing intersection has a complicated 4-way juncture whose safety falls short of optimal standards. The new structure will be up to current standards and improve the drivability and safety for motorists.

The project will involve staged single lane closures in addition to Route 151 being briefly closed with a signed detour.

 

Questions about the project may be directed to CDCR@modot.mo.gov or by phone at 888 ASK MODOT (1-888-275-6636). Please reference the Boone County Route 22, 124, and 151 Roundabout.

Use the form above to sign up for project-specific updates. As the project moves into the construction phase and a schedule is known, updates will be provided on MoDOT's Central District on social media. 