Work suspended for winter. Updated 12/01/2022

This is one bundle of routes to be resurfaced as part of Gov. Parson's Rural Road program. To learn more about the program, please visit www.modot.org/governors-rural-roads-program

 

Counties Impacted
Carroll
Linn
Livingston
Grundy
Project Status
In Progress
Route Impacted
Missouri Route 139
Route K
Route KK
Route BB
Route JJ
Route Z
Route C
Route YY
Route U
Route Y
Embed
Routes included in this bundle
Summary

Completed routes = green

Scheduled routes = orange

Future routes = blue

Is Responsive
Embed Code

Emery Sapp & Sons, Inc., working with the Missouri Department of Transportation, will resurface the routes according to the schedule listed below (subject to change):

  • Grundy/Linn County Route 139 from Grundy County Route 6 at Humphreys to the Parsons Creek Bridge north of Linn County Route B - scheduled for 2023
  • Grundy/Livingston County Route K - scheduled for 2023
  • Grundy/Livingston Route U - scheduled for 2023
  • Livingston Route Y - scheduled for 2023

Emery Sapp & Sons, Inc. completed the resurfacing of the following routes in 2022:

  • Linn County Route 139 from the Parsons Creek Bridge north of Route B to U.S. Route 36
  • Livingston/Linn County Route BB from Route KK to Route B along the Livingston/Linn County line
  • Livingston County Route KK from Route BB at the Linn County Line to the end of state maintenance
  • Livingston County Route JJ from U.S. Route 65 to Route H in Avalon
  • Carroll County Route YY from Route J to Route M
  • Carroll County Route C from Route D to Route Z
  • Livingston/Carroll County Route Z from U.S. Route 65 to U.S. Route 65

Project News