Counties Impacted
Jasper
Newton
In Progress

Project Facts:

  • Remove and replace 1.4 miles of concrete pavement on I-49 between I-44 and a point south of Jasper County Route FF (32nd Street) in Joplin
  • Concrete is part of original pavement built as part of I-49 construction in 1994
  • Concrete deteriorating and being replaced due to high traffic volumes

Construction: Week of April 5 until early August

Total Project Cost: $6.2 million

Traffic Impacts:

Phase 1:

  • All lanes of southbound I-49 CLOSED ’round the clock for up to 16 days for pavement
  • replacement
  • All lanes of northbound I-49 open
  • Route FF (32nd Street) southbound ramps will be CLOSED in the direction of the work being done
  • Expect increased travel times
  • Drivers will be directed to signed detour using Business Loop 49, I-44 and Missouri Route 59

Phase 2:

  • All lanes of northbound I-49 CLOSED ‘round the clock for up to 16 days for pavement
  • replacement
  • All lanes of southbound I-49 open
  • Route FF (32nd Street) northbound ramps will be CLOSED in the direction of the work being done
  • Expect increased travel times
  • Drivers will be directed to signed detour using Business Loop 49, I-44 and Missouri Route 59