Counties Impacted
Platte
Route Impacted
29
Completed

Project Update

Complete
Project Update: Spring 2023

Improvements are also being made to Route AA (NW Waukomis Drive) underneath I-29, between the northbound and southbound on and off ramps. The project is scheduled to be completed in Spring/Summer of 2023. Improvements include:

  • Sidewalks
  • ADA upgrades
  • Enhanced lighting 
milestone_icon
Complete
Project Update: September 2022

Crews are constructing bridge walls and installing supports for the I-29 bridge over Route AA (NW Waukomis Drive). Currently, most of the construction and installation is taking place on the northbound side of I-29, under the bridge, and will throughout the month of September 2022.

milestone_icon
Complete
Project update: Summer 2022

Crews are completing bridge demolition and cleanup of the existing I-29 northbound bridge. Construction of the new bridge is under way. Improvements are also being made to Route AA (NW Waukomis Drive) underneath I-29, between the northbound and southbound on and off ramps.

milestone_icon
Complete
Project Update: 3/21/2022 (Waukomis Bridge)

Work to begin replacing the old I-29 & Waukomis Dr. Bridge will begin Wednesday, March 23.

milestone_icon
Complete
Project Update: 11/17/2021 (56th St. Bridge)

The I-29 Bridge over 56th St. project is now complete!! Thanks for your patience. 

*Crews will begin the I-29 Waukomis Dr. Bridge project in the spring of 2022. 

 

milestone_icon
Complete
Project Update: 3/5/2022 (Waukomis Bridge)

Crews will close various lanes of northbound and southbound I-29 between North Oak Trafficway and 56th St. from Wednesday, March 23 until Thursday, Dec. 1 for bridge work

Crews will close the Route 169 northbound ramp to I-29 northbound from Wednesday, March 23 until Thursday, Dec. 1 for bridge work

Crews will the Route 169 southbound ramp to I-29 northbound from Wednesday, March 23 until Thursday, Dec. for bridge work

Crews will close the I-635 northbound ramp to I-29 southbound from Wednesday, 23 until Thursday, Dec. 1 for bridge work 

Crews will close various lanes of northbound and southbound NW Waukomis Dr. underneath I-29 between NW 53rd Terr. from Wednesday, March 23 until Thursday, Dec. 1 for bridge work 

milestone_icon
Complete
Project Update: 11/16/2021 (56th St. Bridge)

Good news! The I-29 and 56th St. Bridge replacement project is wrapping up ahead of schedule.

Crews have opened all lanes of northbound I-29 over 56th St.

Crews have opened I-635 northbound to I-29 northbound.

Crews have opened the I-29 northbound on-ramp from Gateway.  

milestone_icon
Complete
Project Update: 11/5/2021 (56th St. Bridge)

Crews are just a few weeks away from completing the project. We're almost there!!! 

milestone_icon
Complete
Project Update: 10/22/2021 (56th St. Bridge)

Crews have begun work on erecting the barrier walls on the top portion of I-29.

Crews are also working  down below on 56th St. Most notably, they are demolishing the old pavement and installing new pavement.

At present, crews hope to have the overall project complete by the second week of November, depending on the weather.  

milestone_icon
Complete
Project Update: 8/2/2021 (56th St. Bridge)

Crews will close the northbound and southbound lanes of Prairie View Rd. between Adrian Ave. and the southbound I-29 on-ramp from 3am, Monday, August 9 until 9pm, Friday, September 3 for roadway construction work.

Crews will close the I-29 southbound on-ramp from Prairie View Rd. and 56th St. from 3am, Monday, August 9 until 9pm, Friday, September 3 for roadway construction work. 

milestone_icon
Complete
Project Update: 7/9/2021 (56th St. Bridge)

Crews will begin shifting northbound I-29 traffic at 56th St. to the southbound lanes, starting Thursday, July 15 and Friday, July 16. Southbound traffic of I-29 will remain in the southbound lanes.    

milestone_icon
Complete
Project Update: 3/8/2021 (56th St. Bridge)
  • Crews will close all eastbound and westbound lanes of 56th St. underneath I-29 between Roanridge Rd. and Prairie Vied Rd. from 8:00 p.m. Monday, March 15 until Wednesday, Nov. 17 for bridge work
  • Crews will close the I-29 ramp northbound to 56th St./Roanridge Rd. from 8:00 p.m. Monday, March 15 until 6:00 a.m. Wednesday, Nov. 17 for bridge work
  • Crews will reduce northbound and southbound I-29 at the 56th St. Bridge to two lanes from 8:00 p.m. Monday, March 15 until 6:00 a.m. Wednesday, Nov. 17 for bridge work
  • Crews will close the NW Gateway (Route A) Ramp to I-29 northbound from 8:00 p.m. Monday, March 15 until 6:00 a.m. Wednesday, Nov. 17 for bridge work
  • Crews will close the I-635 northbound ramp to I-29 northbound from 8:00 p.m. Monday, March 15 until 6:00 a.m. Wednesday, Nov. 17 for bridge work

Motorists are encouraged to look for posted detour routes while this project is underway. There are multiple interstate detours available. For southbound I-29 traffic, motorists can take eastbound 152, to southbound 169, and back to I-29.

milestone_icon

Project Information 

Project Goal: MoDOT will be replacing the I-29 Bridge over 56th St. and the Waukomis Drive Bridge in Platte County. The two bridges have reached their projected service life.  

This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

ONLINE PUBLIC MEETING: The Missouri Department of Transportation held an online public information meeting, beginning Monday, Oct. 26, 2021 and continuing until Monday, Nov. 9, 2021 regarding the replacement of two bridges along the Interstate 29 corridor in Platte County, MO. Please scroll down to the comment form below after reviewing the project information and plans.

How will this project benefit me? 

This project will provide two new and safer bridges. It will also add sidewalk/share use path and lighting underneath the bridges. A left turn lane will be added to 56th Street and Waukomis Drive/Rte AA for additional traffic safety. 

What is the time line for this project?

Both bridge projects are anticipated to begin in spring of 2021 and expected to be completed by the spring of 2023.

How will this project impact traffic? 

In order to minimize impacts on I-29 traffic, some ramps and roads will be closed during different phases. Detours will be in place during construction.

 

What will this project cost? How will the project be funded? 

The construction cost for these two projects is approximately $7 Million dollars and is funded with MoDOT funding.

 

Bridge Facts: 

    I-29 & 56th St. Bridge 

  • Built in 1967
  • It is a set of concrete slab twin bridges
  • Each slab is 121' long and a roadway width of 52' 
  • Both bridges have around 55,000 vehicles daily 

     I-29 & Waukomis Drive Bridge 

  • This bridge was originally built in 1957 (concrete deck girder bridge)
  • It was widened in 1974 (adjacent pre-stressed box girder bridge)
  • It is 123' long and has a roadway surface of 138' wide
  • This bridge has around 90,000 vehicles daily 

Project News

Share your comments or leave a question about this project 

Webform

Project Progress photos

Embed
Summary

Check out these photos of progress on the project. 

Is Responsive
Embed Code
I-29 & Waukomis Dr. Bridge Replacement 2022