Counties Impacted
Greene
Project Status
In Progress

Project Facts:

Rebuild the 1950s-era concrete pavement in four locations:

  • Near Lombard Street
  • North of Commercial Street underneath railroad bridge
  • At Kearney Street - COMPLETED
  • At Evergreen Street - COMPLETED

Estimated total project cost: $3.7 million

Traffic Impacts

  • 'Round the clock lane closings on Glenstone Avenue for several weeks at a time
  • Side streets closed at times
  • Right and left turns, through lanes restricted at times
  • Major traffic delays expected
  • Drivers urged to find alternate routes unless visiting businesses along Glenstone Avenue
  • Work on Glenstone project will be coordinated with nearby projects including a bridge and pavement rebuild project on southbound Route 65 between Valley Water Mill Road and Kearney Street

Project Updates

  • Glenstone Avenue Pavement Rebuild

    10/09/2018
    • Outside lanes of northbound and southbound lanes closed on Glenstone Avenue between Lombard and Page Streets until week of Oct. 15 – DELAYS OCCURRING
    • Southbound U.S. Route 65 to Kearney Street (Missouri Route 744) off ramp CLOSED 8 p.m. to 10 p.m.,...
  • Glenstone Avenue Pavement Rebuild

    09/28/2018
    • Outside lanes of northbound and southbound lanes closed on Glenstone Avenue between Lombard and Page Streets north of Sunshine Street until week of Oct. 7 – DELAYS OCCURRING
    • Page and Lombard Streets at Glenstone Avenue CLOSED Monday night, Oct. 1 

    W...

  • TRAFFIC ALERT

    09/26/2018

    What: Rebuilding street approaches at Lombard and Page Streets at Glenstone Avenue in Springfield 

    When: 7 p.m.-7 a.m. Friday into Saturday, Sept. 28-29 

    Traffic Impacts:

    • Drivers will not be able to access Glenstone Avenue from Lombard or Page...
  • Glenstone Avenue Pavement Rebuild

    09/21/2018
    • Glenstone Avenue reduced to one lane in each direction and traffic shifted to NORTHBOUND lanes at railroad bridge north of Commercial Street – DELAYS OCCURRING
    • EARLY HEADS UP: Traffic shifting to outside lanes of northbound and southbound lanes on...
  • Glenstone Avenue Pavement Rebuild

    09/14/2018
    • Glenstone Avenue reduced to one lane in each direction and traffic shifted to southbound lanes at railroad bridge north of Commercial Street – DELAYS OCCURRING
    • Inside northbound and southbound lanes closed on Glenstone Avenue between Lombard and...
  • Glenstone Avenue Pavement Rebuild

    09/07/2018
    • Glenstone Avenue reduced to one lane in each direction and traffic shifted to southbound lanes at railroad bridge north of Commercial Street 

    Work Scheduled:  

    • Removing concrete pavement in northbound lanes of Glenstone Avenue underneath railroad...
  • Glenstone Avenue Pavement Rebuild Project

    09/04/2018

    Springfield, Greene County – A project to rebuild the deteriorating concrete pavement at four separate locations on Glenstone Avenue in Springfield is scheduled to resume the week of Sept. 10 – a delayed restart date, the Missouri Department of...

  • Glenstone Avenue Pavement Rebuild Project

    08/28/2018

    Springfield, Greene County – A project to rebuild the deteriorating concrete pavement at four separate locations on Glenstone Avenue in Springfield is scheduled to resume following the Labor Day holiday weekend, the Missouri Department of...

  • Glenstone Avenue Pavement Rebuild

    07/13/2018
    • Work that would impact traffic on Glenstone Avenue suspended until late July or August
    • Weekly project updates suspended until work resumes on project 

    Work Scheduled:  

    • Cleanup and sidewalk work in areas 

    Traffic Impacts:

    • No impacts to traffic...
  • Glenstone Avenue Pavement Rebuild

    07/05/2018
    • Lane closings at Glenstone/Kearney intersection should be complete by end of the week  

    Work Scheduled:  

    • Installing concrete medians at Kearney Street/Glenstone Avenue intersection
    • Building entrances and sidewalks in various locations
    • Repairing...