Forward 44 Environmental Study

Overview

Missouri’s FY2024 budget from the General Assembly signed into law by Gov. Parson provided $20 million of General Revenue for an environmental study more than 250 miles of the I-44 corridor from the Oklahoma state line to the Franklin County/St Louis County line. This study is a critical step to preparing for future projects on I-44. 

Study Goals

The goals for the I-44 corridor environmental study are to validate the outcomes of the 2008 I-44 Purpose and Need Study with the opportunity for the public to provide input and to divide the more than 250 miles of the I-44 corridor into logical independent segments that can further be studied. Those project segments can then be prioritized for further in-depth study to determine a preferred alternative and prepare for detailed design and construction when funds are available.

Next Steps

Two consultants have been hired with the full corridor divided into two. The Forward 44 Study began in early 2024, and work has been done to gather customer feedback and collect data about the current and projected needs along the I-44 corridor. Stakeholder meetings and public meetings occurred throughout summer 2024.  Stakeholder meetings are ongoing at this time.  It is expected the final Purpose and Need document will be completed in Spring 2025 and will include recommendations on how to divide the 250-mile corridor into smaller project segments for future study.

Study Timeline

Complete
February 2024

Two consultants have been hired with the full corridor divided into two. Initial review should begin in early 2024 and will take approximately one year.

milestone_icon
Complete
July-August 2024

Public Meeting Period (5 Meetings )

milestone_icon
In Progress
Spring 2025

Final Purpose and Need document completed.

milestone_icon
Not Started
2025

The next stage on more in-depth review in smaller segments will then begin and could take another two years

milestone_icon
Embed
Summary

Below is an interactive map that shows the 253-mile stretch of I-44 and how it is broken into two sections for the environmental study.

Is Responsive
Embed Code