Counties Impacted
Chariton
Route Impacted
24
Completed
COMPLETE

The Palmer Creek Bridge on Chariton County U.S. Route 24, east of Brunswick, was built in 1958 and carries more than 1,650 vehicles each day. The deck of the bridge was in poor condition and is in need of replacement to improve the condition of the driving surface and extend the life of the structure. The project began Aug. 1, 2022, and was completed Dec. 14, 2022.

Project Progress

Complete
Planning & Design Phase

MoDOT's Planning and Design team, along with a consultant, designed a project which will replace the deck of the Chariton County U.S. Route 24 bridge over Palmer Creek, east of Brunswick.

milestone_icon
Complete
Contract Letting, Award & Notice to Proceed

The project to rehabilitate the Palmer Creek Bridge on Chariton County U.S. Route 24 was part of a bundle of four bridge projects. This bundle was part of the September 2021 letting where contractors submitted competitive bids on the project bundle. The Missouri Highways and Transportation Commission awarded the $2,736,998.45 project to Emery Sapp & Sons, Inc. at their October 2021 meeting. At that time they gave the contractor a Dec. 6, 2021 Notice to Proceed. This is the earliest date the contractor could begin work.

milestone_icon
Complete
Construction

The contractor tentatively plans to being work on the bridge in July 2022. Once construction begins, the contractor has 125 calendar days to complete the work. By contract, all four bridges in this bundle must be complete on or before Dec. 1, 2022 or the contractor may incur liquidated damages.

milestone_icon

Frequently Asked Questions:

Q: Will the road be closed during construction?

A: The project was designed to be completed under staged construction where only one lane is closed at a time. One lane of U.S. Route 24 should remain open, with restrictions, throughout construction.

 

Q: Who can I contact if I have further questions?

A: Questions about the project may be directed to MoDOT's Customer Service team at NWCR@modot.mo.gov or by phone at 888 ASK MODOT (1-888-275-6636).

 

Q: How can I stay updated on the project's progress?

A: Sign up for project-specific updates using the form below.

Project News

  • U.S. Route 24 in Chariton County to narrow near Brunswick

    01/30/2023

    ST. JOSEPH, Mo. – The final work on the Palmer Creek bridge deck replacement project will be completed next week. Emery Sapp & Sons, Inc., working under a contract with the Missouri Department of Transportation to replace the Palmer Creek Bridge...

  • Chariton County bridge project complete

    12/14/2022

    ST. JOSEPH, Mo – A bridge deck replacement project on U.S. Route 24 in Chariton County, west of Route MM near Brunswick, is now complete and the roadway has been restored to normal two-way traffic. Crews from Emery Sapp & Sons, Inc., working with the...

  • Chariton County U.S. Route 24 to close Tuesday night

    09/09/2022

    ST. JOSEPH, Mo. – Guardrail repairs will close both directions of Chariton County U.S. Route 24 east of Brunswick on Tuesday night, Sept. 13, at the site of the Palmer Creek Bridge deck replacement project. Contractors working with the Missouri...