Counties Impacted
Carroll
Route Impacted
Z
Completed

Project Progress

Complete
Design phase

The Missouri Department of Transportation designed a new bridge over Tater Hill Creek on Route Z in Carroll County.

milestone_icon
Complete
Contractors bid on the project

The project was part of MoDOT's Aug. 21, 2020 bid letting where contractors were able to submit competitive bids on construction projects.

milestone_icon
Complete
Contract awarded

The Missouri Highways and Transportation Commission awarded a $713,529.45 contract to E & C Bridge, LLC at their Sept. 2, 2020 meeting.

milestone_icon
Complete
Notice to proceed

The contractor was given a Sept. 10, 2020 Notice to Proceed, which is the earliest date a contractor can begin work on the project.

milestone_icon
Complete
Construction begins and road closure

The contractor closed the roadway to all traffic and began work on the new bridge construction on Monday, Sept. 21, 2020. The road was reopened to all traffic on Monday, Nov. 23, 2020, ahead of schedule.

milestone_icon
Complete
Road reopening

The contractor reopened the road to all traffic on Monday, Nov. 23, 2020, ahead of schedule.

milestone_icon
Image
Carroll County Route Z bridge over Tater Hill Creek

Old Bridge

- single-lane bridge

- one 16-foot lane

- entire bridge: 20-feet wide

Image
Plans for new Carroll County Route Z bridge over Tater Hill Creek

New Bridge

- two-lane bridge

- two 10-foot lanes

- entire bridge: 24-feet wide

Frequently Asked Questions

 

Q. Why is MoDOT closing the road during construction?

A. Closing the road during the bridge replacement saves taxpayer money by allowing the contractor to work more efficiently. This will result in a shorter construction period.

 

Q. How long will the road be closed?

A. Through mid-December

 

Q. What is the detour?

A. A signed detour  is not planned.

 

Q. Why not build a bypass?

A. Based on the cost/benefit ration, building a bypass would not be a prudent use of taxpayer funds. A bypass also could have negative impacts and disruption to private property.

 

Q. Who can I contact if I have further questions?

A. Questions about the project may be directed to MoDOT Customer Service at 888 ASK MODOT (1-888-275-6636).

 

Q. How can I stay updated on the project's progress?

A. Sign up for project-specific updates using the form below.

  • Carroll County bridge replacement project complete

    11/25/2020

    TINA, Mo. – The bridge over Tater Hill Creek on Carroll County Route Z is now open to all traffic. Closed since Sept. 21, the bridge reopened late in the day Monday, Nov. 23. The Missouri Department of Transportation contracted with E & C Bridge LLC...

  • Carroll County bridge replacement project to begin Monday

    09/14/2020

    TINA, Mo. – The bridge over Tater Hill Creek on Carroll County Route Z will be replaced beginning next week. The Missouri Department of Transportation contracted with E & C Bridge LLC to replace the structurally deficient 86-year old bridge. This...

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636).