Districts Impacted
Project Summary
From 2022 to 2026, MoDOT has three planned resurfacing projects to address the aging pavement on Caldwell/Daviess County Route 13 between Ray County and Missouri Route 6 in Gallatin.
Active Project(s):
On May 1, 2023, Phillips Hardy, Inc., working with the Missouri Department of Transportation, started a resurfacing project on Route 13 from the southern city limits of Hamilton to north of Route HH in Kingston.
Crews will begin stage 3 of the project on Monday, April 1, 2024.
- Route 13 will be CLOSED from Far West Drive to north of Route HH in Kingston (April 1 to mid-June).
Project Timeline
Kingston to the Ray County line - complete November 2022.
Route 13 bridge over U.S. Route 36:
- A project to rehabilitate the Caldwell County Route 13 bridge over U.S. Route 36 was part of MoDOT's Oct. 2022 letting for contractor bidding.
- A $2,038,133.61 contract to complete the project was awarded to Capital Paving & Construction, LLC. Construction began on May 30, 2023. The project was completed on Aug. 14. For more info: Caldwell County Route 13 bridge over U.S. Route 36 Rehabilitation Project | Missouri Department of Transportation (modot.org)
Route 13 Resurfacing Project:
- Stage one of resurfacing from the south city limits of Hamilton to north of Route HH in Kingston began in early May 2023.
- Route 13 from Mill Creek Drive to Route P reopened on Dec. 1, 2023.
Contractors from Phillips Hardy, Inc., will begin stage three of the project on April 1, 2024. They will also be completing stage two and making corrections on stage one.
Stage three (Far West Drive to Kingston).
- CLOSED: April 1 to mid-June.
Stage two (Route P to Far West Drive).
- CLOSED: June 5 to mid-August.
Stage one (Mill Creek Drive to Route P).
- April 8 to early June.
- Traffic will be narrowed to one lane in sections from Mill Creek Drive to Route P. Traffic will be directed through the work zones by temporary traffic signals. A 12-foot width restriction will be in place.
Scheduled for the October 2025 letting for contractor bidding.
Project News:
-
Caldwell County Route 13 resurfacing project to resume
ST. JOSEPH, Mo. – Concrete paving on Caldwell County Route 13 is scheduled to begin on Monday, April 1. Contractors from Phillips Hardy, Inc., working with the Missouri Department of Transportation, will continue work to complete stages two (Route P...
-
NOW OPEN: Caldwell County Route 13
ST. JOSEPH, Mo. – Caldwell County Route 13 from Mill Creek Drive to Route P is now open. Contractors from Phillips Hardy, Inc., working with the Missouri Department of Transportation, closed the roadway in May 2023 to begin Stage One (Mill Creek...
-
UPDATE: Caldwell County Route 13 resurfacing project
ST. JOSEPH, Mo. – The project to repave a section of Caldwell County Route 13 from Mill Creek Drive at the southern city limits of Hamilton to north of Route HH in Kingston is continuing to progress. Contractors from Phillips Hardy, Inc., working...
Frequently Asked Questions:
Q: Will MoDOT close the road during construction?
A: For the concrete overlay from Kingston to Mill Creek Road in Hamilton: Yes, in order for the contractor to lay the concrete overlay, and the need of adequate concrete cure time, the roadway will be closed in three different phases in order to complete the project (segments listed below). A detour will direct motorists to use U.S. Route 36, I-35 and Route 116 during the closure. The contractor will work with residents within each work zone to maintain property access during construction.
- Mill Creek Road to Route P
- Route P to Far West Drive
- Far West Drive to just north of Route HH in Kingston
For the resurfacing from Mill Creek Road in Hamilton to Route 6 in Gallatin: It is expected that construction will be completed under single-lane closures. The roadway would remain open, but motorist should anticipate delays.
Q: Why is the road closed instead of narrowed to one lane?
A: The decision to fully close the roadway in three sections was made due to roadway condition, cost and intent to reduce traffic impacts.
-
The design team considered reducing traffic to one lane during construction, however, concrete traffic barriers would have been required to be installed down the center of the roadway, pushing traffic off onto the shoulders of Route 13. Due to the current/previous condition of Route 13, this would have required complete reconstruction of the shoulders prior to completing the overlay. This option was not chosen due to cost, construction time/traffic delays, and restrictive property owner access.
Q: Who can I contact if I have further questions?
A: Questions may be left by calling 888 ASK MODOT (888-275-6636) or emailing nwcr@modot.mo.gov
Q: How can I stay updated on the project's progress?
A: Sign up for project-specific updates at the bottom of this page.
Need More Information?
We're here to help! If you're looking for additional information, you can contact us at:
- nwcr@modot.mo.gov
- 1-888-ASK-MODOT (888 275-6636) - reference Northwest District Caldwell/Daviess County Route 13 projects
- Sign up for eUpdates: Customer Service Signon (mo.gov)