Counties Impacted
Adair
Route Impacted
U.S. Route 63

Project Schedule

Design Public Hearing - May 2, 2019

Public comments will be accepted until May 16, 2019

Summer/Fall 2019

Right of way acquisitions will take place, design completion and possible utility work

Summer/Fall 2020

Public meeting will be held regarding traffic control, final design will be approved

January 2021

Project will be let out for bid to contractors

Summer/fall 2021

Construction is planned to begin

Project Improvements
  • Resurfacing
  • Curb and gutter - eliminate the drop off that currently exists
  • Storm water drainage - eliminate ponding of water on roadway
  • Driveway/business entrances
  • Sidewalks - bring into compliance with ADA
  • Signals - upgrades to accommodate pedestrians and replacing wires

 

Questions?

Keith Killen, P.E.
Title
Project Manager
Department
Northeast District
Contact Info
Amy Crawford, P.E.
Title
Area Engineer
Department
Northeast District
Contact Info