Counties Impacted
Adair
Route Impacted
U.S. Route 63

Project Schedule

Complete
Design Public Hearing - May 2, 2019

Public comments will be accepted until May 16, 2019

Complete
Fall 2019 - Fall 2020

Right of way acquisitions will take place, design completion and possible utility work

Complete
January 2021

Project will be let out for bid to contractors

Project Improvements
  • Resurfacing
  • Curb and gutter - eliminate the drop off that currently exists
  • Storm water drainage - eliminate ponding of water on roadway
  • Driveway/business entrances
  • Sidewalks - bring into compliance with ADA
  • Signals - upgrades to accommodate pedestrians and replacing wires

 