Pulaski County Route T Bridge Rehabilitation

The Pulaski County Route T bridge over the Gasconade River, between Swedeborg and Waynesville, was rehabilitated in 2021. The original bridge was built in 1973.  The bridge reached a point where rehabilitation was necessary. 

Project Details

When: 

Construction is complete.

Cost: 

The contract cost was $1,749,000.

Work Taking Place: 

Rehabilitation of the bridge deck, bridge barrier improvements, increased bridge pier protection, rehabilitation of other bridge components, and improvement of  roadway and safety at both ends of the bridge.

Project Milestones

Complete
Public Comment Period
March 1 - 12, 2021
milestone_icon
Complete
Bid Awarded
June 2, 2021

Missouri Highways and Transportation Commission awarded the contract for the project to West Plains Bridge and Grading, which submitted the low bid of $1,749,000.

milestone_icon
Complete
Project Begins
June 24, 2021
milestone_icon
Complete
Project Completion
October 29, 2021