Below are details about the rehabilitations of the Interstate 44 bridges over Trophy Lane and the eastbound I-44 bridge over Roubidoux Creek in Pulaski County. All three bridges are located east of St. Robert. The bridges reached a point where rehabilitation is necessary to extend their life and usability.
Project Details
When:
April - October, 2022
Cost:
The contract for the project was awarded for $1,976.543.
Work Taking Place:
Crews rehabilitated both eastbound and westbound I-44 bridges over Trophy Lane and the eastbound bridge over Roubidoux Creek in Pulaski County. Crews reconstructed shoulders, removed and replaced the existing asphalt wearing surface, repaired the bridges' substructure, applyied an epoxy coating of substructure concrete, and repaired the sinking pavement on the approach to the bridge.
Project Milestones
The Missouri Highways and Transportation Commission awarded the contract for the project to Lehman Construction, which submitted the low bid of $1,976,543.
Work completed in September, 2022.
Work completed in September, 2022.
Work was completed in October, 2022.
Project News & Updates
-
Bridge Rehabilitations on I-44 to Include Lane Closure
ST. ROBERT – Contractors working for the Missouri Department of Transportation (MoDOT) will begin a series of bridge rehabilitations along Interstate 44 near St. Robert on Monday, April 18.
The first phase of the project will be on the eastbound...