Counties Impacted
New Madrid
Route Impacted
61
80
Work Type
Intersection Improvements
Planning Phase

Project Summary

This safety improvement project includes improving the intersection of U.S. 61 and Route 80 near Matthews, MO. Currently, two alternatives are being explored—installing traffic signals or constructing a roundabout.

Public Meeting Information: Feb. 10, 2026

A public meeting will be held from 4 to 6 p.m. Tuesday, Feb. 10 to discuss improving the intersection of U.S. Route 61 and Route 80 near Matthews, Missouri. The meeting will be held at the Nutrition Center in Matthews, located at 301 West Main St. 

During the meeting, MoDOT will share two alternatives for this safety improvement project—installing traffic signals or constructing a roundabout. The meeting materials include an overview of potential right-of way impacts, cost, and the safety and traffic performance of each alternative. 

Tentatively, construction could begin as early as June 2027. Once work begins, it will be underway for approximately nine months. Motorists should anticipate delays, but the intersection will remain open to traffic during construction. 

Video Simulations

Embed
Summary

Watch the video modeling for each alternative (installing traffic signals or constructing a roundabout)

Is Responsive
Embed Code

Project Timeline

Public Meeting
Feb. 10, 2026
milestone_icon
Tentative Letting
April 2027
milestone_icon
Construction Begins
As early as June 2027
milestone_icon
Completion Anticipated
Approximately 9 months after the start of construction
milestone_icon
Webform

SHARE YOUR THOUGHTS!
U.S. 61/Route 80 near Matthews, MO

Please share your thoughts by submitting the form below by Feb. 24, 2026.  Your comments will be sent directly to the project team. 

*
*

For More Information

Contact Photo
Donna Philpot
Donna Philpot
Title
Project Manager
Department
Southeast District
Contact Info

(573) 472-5347